Lesson 4 of 5

Assessing defects by revenue and customer impact

12 min

Not every defect must be fixed before go-live, and not every "minor" defect is minor. In order to cash, two questions decide how serious a defect is: what does it do to revenue and cash? and what does the customer experience? Technical severity (does the transaction dump?) matters less than business impact.

Low priorityInternal inconvenience, no money at risk: for example, a list report column missing
Customer-facingCustomer sees it but money is right: for example, a typo on the invoice layout
FinancialMoney is wrong but the customer does not see it: for example, revenue on the wrong profit center
Must fixCustomer sees it and money is wrong: wrong prices invoiced, invoices to the wrong recipient, orders that cannot ship
Rating order-to-cash defects by revenue and customer impact.
The Sign-Off Table · thesignofftable.com/academy/sap-sd-303

Rating guide

DefectRevenue / cash impactCustomer impactRating
Contract price not applied; list price billedHigh: overbilling and disputes, delayed cashHigh: wrong invoicesMust fix
Invoice emails sent to the wrong contactMedium: invoices not received, late paymentHigh: confidential data to the wrong personMust fix
Revenue posted without profit centerMedium: margin reporting wrongNoneFix before go-live or first close
Order confirmation shows wrong logoNoneLowFix after go-live
Credit block not triggered above limitHigh: credit exposureNone directlyMust fix
Delivery due list slow for large selectionsLow if workaround existsNoneWorkaround, fix after go-live

Examples of order-to-cash defect ratings at Contoso.

Questions that decide the rating

  1. Does the defect produce a wrong amount for the customer or in the books?Yes → high revenue impact · No → continue
  2. Will the customer see it, or receive something wrong or late?Yes → high customer impact · No → continue
  3. Does it expose personal or confidential data?Yes → treat as must fix regardless of volume · No → continue
  4. Is there a workaround that is safe, documented and sustainable at volume?Yes → may be accepted with an owner and a fix date · No → must fix before go-live
Assessing an O2C defect before the go/no-go discussion.
The Sign-Off Table · thesignofftable.com/academy/sap-sd-303

Volume changes everything

A defect affecting one order in a thousand looks small in a test cycle. At Contoso's volume of roughly 400 orders a day it is several wrong orders every week, each one a call to customer service and possibly a credit memo. When rating, estimate the production frequency: which customers, products or channels trigger it, and what share of orders they represent. A workaround that takes two minutes per order is fine for five orders a week and impossible for five hundred.

Workarounds also need owners. A documented workaround says who does it, when, how it is checked, and when it ends. "Billing team will fix invoices manually" is not a workaround; "Billing clerk checks the daily list of invoices for customer group 02 and corrects the freight condition before release, until fix release 1.2 on August 15" is.

DefectWhat is wrong and how to reproduce it
ImpactRevenue or cash effect and customer effect, with estimated frequency
RatingMust fix, fix before first close, or fix after go-live
DecisionFix now, or accept with a documented workaround, owner and end date
From defect to decision.
The Sign-Off Table · thesignofftable.com/academy/sap-sd-303

Retesting fixed defects

A must-fix defect is closed only when the fix has been retested with evidence, and the scenarios around it have been regression tested. A pricing fix for aftermarket customers can break fleet pricing; a change to output determination can stop order confirmations. For each fix, Priya's team reruns the failing scenario and at least one neighboring scenario that uses the same configuration, and attaches both results to the defect.

What would you do?

Late in UAT, Priya's team finds that invoices for aftermarket customers are sent to the sales contact instead of the accounts payable contact. The developer rates it "low: the invoice is correct, only the recipient is wrong". Maria disagrees. Who is right, and why?

Key points
  • Rate O2C defects by revenue or cash impact and customer impact, not technical severity.
  • Wrong amounts customers see, wrong recipients and missing credit controls are must-fix defects.
  • Estimate production frequency; small test-cycle counts can mean many incidents at volume.
  • Accepted workarounds need an owner, a check and an end date.
  • No open must-fix defects at sign-off.

Check your understanding · not graded

Lesson check

  1. 1. Which two questions decide an O2C defect's seriousness?

  2. 2. A defect sends invoices to the wrong email address. How should it be rated?

  3. 3. What makes a workaround acceptable?

  4. 4. Why estimate production frequency for a defect seen once in testing?