Lesson 2 of 5

The N+1 landscape

9 min

The usual answer to dual maintenance is an N+1 landscape. "N" is the current release, the landscape that supports production today. "N+1" is the next release, the project landscape where the new system is built. Production stays attached to N until cutover. The N+1 track runs beside it with its own development and test systems, and changes flow from N to N+1 through retrofit, never the other way.

N: maintenance trackN+1: project track
ReleaseSAP ECC 6.0 EHP 8SAP S/4HANA 2025 (converted)
DevelopmentED1CMD
QualityEQ1CMQ (client 100 for testing)
ProductionEP1 (live)CMP after cutover
Allowed changesFixes, legal changes, approved small changesProject scope, plus retrofits from N
Change toolExisting ECC change processFeatures in SAP Cloud ALM
Contoso’s N and N+1 tracks. System IDs are illustrative.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-303

How the N+1 track is built in a conversion

SAP's conversion guidance follows a sequence: convert a sandbox made from a production copy first to learn, then convert development, then quality, then rehearse with a production copy, and finally convert production. Each step needs the maintenance track to keep running on the old release. At Contoso, Sam created CMD from a copy of ED1 and converted it; ED1 itself stayed on ECC for maintenance. CMQ followed the same way from EQ1.

  1. SandboxCopy EP1, convert; learn the technical steps and custom code impact
  2. DevelopmentCopy ED1 to CMD, convert; ED1 continues as maintenance development
  3. QualityCopy EQ1 to CMQ, convert; EQ1 continues as maintenance test
  4. RehearsalCopy EP1, convert in rehearsal; measure downtime
  5. ProductionConvert EP1 at cutover; N track retired
Building the N+1 track step by step. The copy date of each system starts its divergence.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-303

Transport routes

The two tracks need separate transport routes so that nothing moves between them by accident. ED1 transports go to EQ1 and EP1. CMD transports go to CMQ and, at cutover, become part of the production build. A transport from ED1 must never be imported straight into CMD or CMQ: the objects there have been converted and adapted, and an old version would overwrite them. Retrofit is a controlled step, not an import.

Clients, users and data in N+1

An N+1 track is more than system copies. Developers and testers need users in both tracks, and it must always be obvious which track they are in, so Sam gives the S/4HANA systems a distinct logon banner and color scheme. Test data in CMQ will age as the project runs; plan refreshes carefully, because a refresh of a project system from ECC production would wipe converted work. The usual answer is to refresh test data in CMQ through migration loads or data tools, not through system copies, once the track is built.

Cost and alternatives

An N+1 track roughly doubles the development and test infrastructure for the length of the project. Smaller programs sometimes accept a longer freeze instead, or keep only an emergency repair copy of production. The trade-off is time versus money: the longer the project, the more an N+1 track pays for itself in flexibility.

Short project, low volumeFreeze ECC and use an emergency repair copy; no full N+1
Long project, low volumeLean N+1: development and quality only; strict freeze
Short project, high volumeCompress the plan; staged freeze plus N+1 for the critical window
Long project, high volumeFull N+1 track with a formal retrofit process and register
Choosing a landscape strategy for dual maintenance.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-303

What would you do?

Kenji needs an ECC user-exit fix in the S/4HANA project system quickly. He asks Sam to add ED1's transport to the CMQ import queue "just this once". What should Sam do?

Key points
  • N is the maintenance landscape supporting production; N+1 is the project landscape.
  • In a conversion, project systems are copies of ECC systems converted step by step; each copy date starts divergence.
  • Keep transport routes separate; never import N transports directly into N+1.
  • An N+1 track costs infrastructure; weigh it against project length and change volume.

Check your understanding · not graded

Lesson check

  1. 1. In an N+1 landscape, what does N+1 refer to?

  2. 2. Why must ECC transports not be imported directly into S/4HANA project systems?

  3. 3. Which SAP conversion step comes first?