Dual Maintenance and Retrofit During Transformation
Course quiz
Dual Maintenance and Retrofit During Transformation
Keep this: job aid
Dual maintenance and retrofit card
- N = maintenance track for production; N+1 = project track. Changes flow N → N+1 by retrofit only.
- No transport routes from N to N+1; never import ECC transports into project systems.
- Register starts the day the first project system is copied; build it from production import history.
- Every change gets a decision: not applicable (with reason), retrofit, or merge.
- Methods: auto-import (no conflict), semi-automatic (Correction Workbench, BC Sets), manual.
- Across ECC to S/4HANA, review code retrofits even without conflicts; re-enter configuration in CMD.
- Freeze stages: open, soft, hard, cutover; publish dates and an emergency procedure.
- Test each retrofit in CMQ; link evidence to its feature; add critical ones to regression.
- Reconcile before cutover and after the last ECC import; sign the register complete.