Dual Maintenance and Retrofit During Transformation

Course quiz

Dual Maintenance and Retrofit During Transformation

Keep this: job aid

Dual maintenance and retrofit card

  • N = maintenance track for production; N+1 = project track. Changes flow N → N+1 by retrofit only.
  • No transport routes from N to N+1; never import ECC transports into project systems.
  • Register starts the day the first project system is copied; build it from production import history.
  • Every change gets a decision: not applicable (with reason), retrofit, or merge.
  • Methods: auto-import (no conflict), semi-automatic (Correction Workbench, BC Sets), manual.
  • Across ECC to S/4HANA, review code retrofits even without conflicts; re-enter configuration in CMD.
  • Freeze stages: open, soft, hard, cutover; publish dates and an emergency procedure.
  • Test each retrofit in CMQ; link evidence to its feature; add critical ones to regression.
  • Reconcile before cutover and after the last ECC import; sign the register complete.