The Sign-Off Table

Lesson 3 of 6

Work centers

9 min

Listen to this lesson

0:00 / 4:28

A work center is where an operation is done: a machine, a line, a test bench or a team. SAP Learning describes it as the master record that supplies data for scheduling, capacity planning and costing. Each routing operation points to a work center, and the work center decides how long the operation takes, how much capacity it uses and what it costs.

Work center (plant 1710)RepresentsActivities confirmedCost center
WIND-10Stator winding machineSetup hours, machine hours (MACHHR)17101104 Detroit Machining
ASSY-10Alternator assembly lineSetup hours, labor hours (ASSYHR)17101101 Detroit Assembly
TEST-10End-of-line test benchMachine hours (MACHHR)17101104 Detroit Machining

Contoso's work centers for the alternator. Names are introduced for this course.

Basic data and the standard value key

The work center's standard value key defines which standard values an operation at this work center carries: for example setup time, machine time and labor time, each with a unit such as minutes or hours. Up to six standard values are possible. The routing then fills in the numbers per operation; the work center only defines the meaning.

The work center ties four things together: which standard values operations carry, what capacity is available, and which cost center and activity types price the work.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-201

Capacity and scheduling

On the capacity side, the work center has one or more capacity categories (machine, labor) with an available capacity: working hours per day, number of individual capacities, and a utilization percentage. Formulas combine the operation's standard values with the order quantity to calculate execution time and capacity requirements. If the formula for machine time is "standard value times quantity divided by base quantity", a routing value of 30 minutes of assembly labor per alternator becomes 50 hours for an order of 100.

  1. Routing operationStandard values: setup 30 min, machine 10 min per piece (WIND-10)
  2. Work center formulasDuration and capacity requirement calculated for the order quantity
  3. SchedulingOperation dates from duration plus queue and move times
  4. Capacity loadRequirement compared with available capacity per day
  5. CostingActivity quantities × activity price of the cost center
One set of standard values feeds scheduling, capacity and cost through the work center.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-201

The cost center link

On the costing tab, the work center is assigned to one cost center at a time (time-dependent), and each standard value is linked to an activity type with a formula that calculates the activity quantity. Controlling plans an activity price per activity type for that cost center and fiscal year. When the order is costed or confirmed, activity quantity times activity price gives the cost; the order is debited and the cost center credited.

Work center ASSY-10Standard value key with setup and labor; formulas per activity
Cost center: 17101101 Detroit AssemblyAssigned on the costing tab, valid from a date
Activity typesSetup hours and labor hours, linked to the standard values
Activity pricesPlanned per cost center, activity type and fiscal year in controlling
Production orderDebited with activity quantity × price on confirmation
How a work center turns minutes into money. Missing prices show up as zero-cost operations.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-201

Capacity data is only as useful as it is honest. If ASSY-10 is maintained with two shifts of eight hours at 100% utilization, but the line really runs about 85% after breaks and changeovers, every capacity evaluation shows free time that does not exist, and orders scheduled to the minute will slip. Ask the production supervisor for real shift patterns and a realistic utilization, and keep the factory calendar for plant 1710 current with holidays and planned shutdowns.

Utilization turns nominal shift hours into real available capacity: maintaining 100% at ASSY-10 shows 2.4 hours a day that the line never has.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-201

What would you do?

Dan notices that the alternator's new cost estimate is $25 lower than last year, and the routing has not changed. Which explanation should you check first?

Activity typeSender cost centerPrice (fiscal year)Per CMC-ALT-100Cost
ASSYHR assembly labor17101101 Detroit Assembly$52 per hour0.5 h$26.00
MACHHR machine time17101104 Detroit Machining$96 per hour0.25 h$24.00

How the routing's standard values become the $50 of labor and machine cost in the $150 standard cost of CMC-ALT-100.

Key points
  • Work centers supply data for scheduling, capacity planning and costing.
  • The standard value key defines up to six standard values; routings hold their numbers.
  • Formulas turn standard values and quantity into durations, capacity requirements and activity quantities.
  • Each work center links to one cost center at a time; activity prices come from controlling.

Check your understanding · not graded

Lesson check

  1. 1. What does the standard value key on a work center define?

  2. 2. How many cost centers can a work center be assigned to at one time?

  3. 3. Where do the numbers for setup and machine time per operation come from?

  4. 4. An operation shows zero cost in the cost estimate. Which is a likely cause?