The go/no-go meeting

10 min

The go/no-go meeting turns all the readiness work into one decision. Done well, it is short, calm and boring: the criteria are known, the evidence has been reviewed, and the discussion focuses on the few items that are not green. Done badly, it is a long argument at midnight. This lesson shows how to run it and how to record and communicate the result.

Before the meeting

  • Circulate the readiness scorecard 24 hours ahead: each criterion, its threshold, actual status and evidence link.
  • Each process owner submits a written recommendation for their process: go, conditional go or no-go, with reasons.
  • Risk acceptances and data acceptances are signed before the meeting, not during it.
  • Agree who decides, who attends and who is consulted. Keep the decision group small.

Running the meeting

  1. Purpose and rulesDecision maker, criteria, and the three possible outcomes are restated
  2. Cutover statusLuis reports execution against plan and decision points
  3. Exceptions onlyWalk through criteria not met; process owners give their recommendation
  4. ConditionsFor each exception: accept, condition with owner and deadline, or no-go
  5. DecisionSteering committee decides; dissent is recorded
  6. CommunicateAgreed message to the business within the hour
Agenda for a go/no-go meeting.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-303

Spend the meeting on exceptions. If 40 of 46 criteria are met, read them as a block and spend the time on the six that are not. For each, the owner states the gap, the impact, the proposed condition or workaround, and their recommendation.

Three outcomes

OutcomeWhenWhat is recorded
GoAll criteria met, or misses formally accepted with no conditions neededDecision, decision maker, date and time, scorecard version
Conditional goSome criteria not met but covered by conditions with owners and deadlinesEach condition, owner, deadline, and what happens if it is missed
No-goA criterion with high impact is not met and cannot be conditionedReasons, what must change, and the date of the next decision
Go/no-go outcomes and what to record.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-303

The decision record

FieldContoso example
Decision and timeConditional go, Sunday 16:20
Decision makerExecutive sponsor, on recommendation of the steering committee
Process recommendationsO2C: go (Dan, Maria). P2P: conditional go (bank interface). R2R: go
ConditionsBank interface fixed and tested before Thursday payment run (owner: integration lead); manual bank upload as fallback (owner: AP lead)
Accepted risksDEF-0412 (delivery note PO number, plant 1720) with workaround; credit review for customer group 03
Data acceptanceSigned for all objects; payables difference for Lakeside Components explained (duplicate invoice in ECC, cleared before go-live)
DissentNone recorded
Next reviewHypercare daily stand-up Monday 08:00; conditions reviewed Wednesday

A go/no-go decision record.

Record dissent. If a process owner recommended no-go and was overruled, the record should say so, with the risk the steering committee accepted. That protects both the process owner and the organization: the decision was made knowingly, by the right people.

Keep the decision record with the program's sign-off pack, next to the UAT sign-offs, data acceptances and risk acceptances. Together they tell the story of how the go-live decision was made. Auditors, new process owners and the next upgrade team will all look for it, and the conditions in it are the starting agenda for the first hypercare reviews.

Communicating the outcome

Tell the business quickly and plainly what was decided, what it means for them on Monday, and what is different from normal. For a conditional go, name the workarounds people will use. For a no-go, say what happens to the legacy system (re-opened for business as usual), when the next attempt is planned and what triggered the decision. Avoid blame; a well-made no-go is a success of governance.

What would you do?

In the go/no-go meeting, Contoso's CFO says, "We've announced Monday to customers; let's just go." Dan's O2C recommendation is conditional go, with one condition: invoice output for Chicago must be fixed by Wednesday. What should Dan say?

Key points
  • Circulate the scorecard and written process recommendations before the meeting; sign acceptances beforehand.
  • Spend the meeting on exceptions; for each, accept, condition or no-go.
  • Record the decision, decision maker, conditions with owners and deadlines, accepted risks and dissent.
  • Communicate the outcome to the business quickly and plainly, including workarounds.

Check your understanding · not graded

Lesson check

  1. 1. What should be circulated 24 hours before the go/no-go meeting?

  2. 2. How should the meeting spend most of its time?

  3. 3. Why record dissent in the decision record?

  4. 4. Which outcome fits misses covered by conditions with owners and deadlines?