Leading Go/No-Go and Cutover Sign-Off
Course quiz
Leading Go/No-Go and Cutover Sign-Off
Keep this: job aid
Go/no-go card
- Five dimensions: process, data, people, technology, support; 1–3 measurable criteria each.
- Get criteria approved by the steering committee weeks before cutover.
- Challenge green: execution, coverage, open defects, retests after late fixes; pick your own evidence sample.
- People readiness: training by role and site; production roles assigned and tested.
- Data acceptance: reconcile counts, totals and samples for master data, open items, G/L balances, stock and open orders.
- Financial balances tie to the cent or every difference is explained.
- Cutover: decision points with criteria and a decision maker; rollback triggers agreed in advance.
- Continuity: every blackout and workaround step has a named owner and was rehearsed.
- Meeting: scorecard 24 hours ahead; discuss exceptions only; go, conditional go or no-go.
- Record decision, conditions with owners and deadlines, accepted risks, dissent; communicate within the hour.