The Sign-Off Table
Leading Go/No-Go and Cutover Sign-Off

Course quiz

Leading Go/No-Go and Cutover Sign-Off

Keep this: job aid

Go/no-go card

  • Five dimensions: process, data, people, technology, support; 1–3 measurable criteria each.
  • Get criteria approved by the steering committee weeks before cutover.
  • Challenge green: execution, coverage, open defects, retests after late fixes; pick your own evidence sample.
  • People readiness: training by role and site; production roles assigned and tested.
  • Data acceptance: reconcile counts, totals and samples for master data, open items, G/L balances, stock and open orders.
  • Financial balances tie to the cent or every difference is explained.
  • Cutover: decision points with criteria and a decision maker; rollback triggers agreed in advance.
  • Continuity: every blackout and workaround step has a named owner and was rehearsed.
  • Meeting: scorecard 24 hours ahead; discuss exceptions only; go, conditional go or no-go.
  • Record decision, conditions with owners and deadlines, accepted risks, dissent; communicate within the hour.