Readiness dimensions

10 min

The go/no-go decision is the most visible decision a process owner makes on an SAP program. It is also the one most often made on gut feel, late at night, with a steering committee that wants to hear "go." This course gives you a way to make it on evidence. It starts by splitting readiness into five dimensions, each with a threshold agreed well before the meeting.

Five dimensions of readiness

ProcessProcesses tested and accepted; open defects fixed or formally accepted
DataMaster data, open items, balances and stock migrated and reconciled; data acceptance signed
PeopleUsers trained and assigned the right roles; key users ready to support; workarounds understood
TechnologyProduction system, interfaces, output, printers, jobs and authorizations ready; performance acceptable
SupportHypercare team, service desk, escalation paths and SAP support contacts in place
The five readiness dimensions a go/no-go decision covers.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-303

In SAP Activate, the go-live decision falls at the end of the Deploy phase, after integration and user acceptance testing and the cutover rehearsals. SAP's own onboarding material describes go-live acceptance criteria as predefined conditions that must be met before launch, with examples such as test completion rates, the number of users trained, the review of open support cases by priority, and validation of migrated data. The point is in the word predefined: the criteria are agreed in advance, not invented in the meeting.

Setting thresholds

For each dimension, write one to three criteria with a clear threshold. Make them measurable, the same way as acceptance criteria. Here is Contoso's set for order-to-cash:

DimensionCriterionThreshold for "go"
ProcessUAT scenarios executed and passed with evidence100% executed; 0 critical and 0 high open unless formally accepted
ProcessRegression of interfaces to carrier and bankAll passed in the final mock cutover
DataCustomer master, open receivables and open sales orders reconciledSigned data acceptance; differences explained or accepted
PeopleEnd users trained and roles assigned95% of O2C users trained; 100% of roles assigned and tested
TechnologyOutput and printing for deliveries and invoices in productionTested in production during cutover with sample documents
SupportHypercare roster and key-user floor supportNamed people for every shift of the first two weeks

Contoso order-to-cash go/no-go criteria. Thresholds are examples; agree your own.

Fix if time allowsBelow threshold, low impact. May go with a workaround and owner.
GoMet, low impact. No discussion needed.
No-go or explicit acceptanceBelow threshold, high impact. Requires a formal decision with conditions or a delay.
Go, confirm evidenceMet, high impact. Sample the evidence before relying on it.
Reading each criterion: readiness against impact.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-303

A threshold does not have to be 100% to be useful. Training 95% of users can be fine if the remaining 5% are named, scheduled and supported by key users in their first week. What matters is that the number was chosen deliberately, with its consequences understood, and that the plan for the gap is written down. Dimensions also interact: a weaker people score can be offset by stronger support, for example extra floor support in the Chicago warehouse, but that trade-off should be an explicit decision, not an accident.

Who decides what

A clear split of roles avoids a meeting where everyone defers to everyone else. The process owner recommends go or no-go for their process, based on the criteria. The cutover manager (Luis, at Contoso) reports execution status and technical readiness. The PMO lead (Grace) consolidates the picture across processes. The steering committee or executive sponsor makes the final decision. A process owner's "no-go" for a critical process should be very hard for the steering committee to overrule without documented risk acceptance.

What would you do?

Two days before the go/no-go meeting, Grace suggests replacing Contoso's data criterion "open receivables reconciled with differences explained" with "data migrated successfully," because reconciliation is behind. What should Dan do?

Key points
  • Readiness has five dimensions: process, data, people, technology and support.
  • Go-live acceptance criteria are predefined, measurable and approved well before the meeting.
  • Read each criterion against its threshold and its business impact.
  • Process owners recommend for their process; the steering committee decides; roles are explicit.

Check your understanding · not graded

Lesson check

  1. 1. Which is NOT one of the five readiness dimensions?

  2. 2. In SAP Activate, when does the go-live decision fall?

  3. 3. What does "predefined" mean for go-live acceptance criteria?

  4. 4. Who makes the final go-live decision at Contoso?