Lesson 5 of 6

Open defects and risk acceptance

10 min

Very few SAP releases go live with zero open defects. That is acceptable, as long as every open defect is known, assessed and owned. Risk acceptance is the formal way for the business to say: we know this is not fixed, we understand what it means, we have a way to work around it, and here is when it will be fixed.

Must-fix versus can-defer

DeferRare and minor. Log, plan a fix, no workaround needed.
Defer with workaroundRare but serious. Document a workaround and who runs it.
Defer with workaround and early fixFrequent but minor. Workaround plus a fix date soon after go-live.
Must fixFrequent and serious. Fix before go-live or do not go.
Classify open defects by impact and likelihood.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-203

Severity alone is not enough. A high-severity defect that only affects one rare scenario may be deferrable with a workaround; a medium defect that hits every billing document may not. Ask both questions: how bad, and how often.

What a risk acceptance contains

FieldContoso example
Defect ID and descriptionDEF-0412: delivery note prints without the customer PO number for orders from plant 1720
Business impactGreat Lakes Fleet Services receiving docks may query deliveries; no financial impact
LikelihoodAll Chicago deliveries, about 40 per week
WorkaroundShipping team writes the PO number on the note; Maria briefs the team
Workaround ownerChicago shipping supervisor
Fix owner and due dateOutput team; fix in the first post-go-live release, by 30 days after go-live
Accepted byDan, process owner, with date
ReviewChecked weekly in hypercare until closed

Contents of a risk acceptance.

Who can accept

Only someone who owns the business consequence can accept the risk. For a process defect that is the process owner. For a defect with financial reporting impact, finance leadership and often internal control should agree. For a defect touching legal or tax requirements, the relevant function must sign too. The test lead and PMO can recommend, but they cannot accept business risk on the business's behalf.

  1. TriageTest lead confirms severity, impact and likelihood
  2. OptionsFix before go-live, or defer with workaround
  3. Workaround testedKey user proves the workaround works
  4. AcceptProcess owner (plus finance or control if relevant) signs with fix date
  5. TrackReviewed in hypercare until fixed and verified
From open defect to accepted risk.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-203

Risk acceptance is also a communication tool. The people who will run the workaround, such as the Chicago shipping team in the example, need to hear about it before go-live, not discover it on the first morning. Include accepted risks and their workarounds in end-user training and in the hypercare briefing, and give the service desk a short note so they recognize the issue when users report it.

Avoiding the common traps

  • Do not downgrade severity to make a gate pass. Accept the risk at its real severity.
  • Do not accept defects without a fix date. "Later" is not a date.
  • Do not accept a pile of individually small defects without asking what they do together in one process.
  • Do not let accepted risks disappear after go-live. They belong on the hypercare agenda.

What would you do?

At the UAT exit gate, Contoso has one open high-severity defect: the credit check does not block orders for a small customer group that places about two orders a month. A manual credit review is possible. What should Dan do?

Key points
  • Classify open defects by impact and likelihood, not severity alone.
  • A risk acceptance names the impact, workaround, owners, fix date and who accepted.
  • Only the owner of the business consequence can accept the risk.
  • Never downgrade severity to pass a gate; track accepted risks through hypercare.

Check your understanding · not graded

Lesson check

  1. 1. Which two questions classify an open defect for deferral?

  2. 2. Which item must a risk acceptance include?

  3. 3. Who can accept business risk for a process defect?

  4. 4. What should happen to accepted risks after go-live?