Lesson 3 of 6

Quality gates

10 min

Acceptance criteria describe the end. Quality gates control the journey. Each test phase has entry criteria (what must be true before it starts) and exit criteria (what must be true before it ends). A gate is the decision point where someone checks those criteria and says go or no-go.

Test phases in SAP Activate

SAP Activate places most testing in the Realize phase: unit tests and string tests (informal), then business role tests, end-to-end process tests, integration and data migration tests, and user acceptance testing (formal and documented). Regression testing continues into Run, every time the system changes. Activate also uses quality gates at phase transitions, and SAP Cloud ALM provides a quality gates capability for recording gate checks and approvals.

  1. Realize, earlyUnit and string testConfiguration and developments work in isolation and in short chains
  2. Realize, middleIntegration test (SIT)End-to-end processes across modules and interfaces, with migrated data
  3. Realize, lateUser acceptance test (UAT)Business users confirm processes meet the acceptance criteria
  4. DeployCutover rehearsal and go/no-goReadiness confirmed; decision to go live
  5. RunRegressionEvery upgrade, feature pack and change re-proves what matters
Where test phases and gates fall in SAP Activate.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-203

Entry and exit criteria by phase

PhaseEntry criteria (examples)Exit criteria (examples)
Unit / stringDesign approved; configuration transported to QAS client 100All unit tests executed; no open defects that block integration
IntegrationUnit exit met; interfaces connected; migrated test data loaded; roles assigned100% of integration scenarios executed; 0 open critical; high defects fixed or accepted
UATIntegration exit met; testers trained; acceptance criteria approved; UAT data readyAll UAT scenarios executed with evidence; 0 critical and 0 high open unless formally accepted; process owner sign-off
RegressionChange scope known; regression set selected by riskSelected set passed; deviations explained; release approved
Entry and exit criteria for the main test phases. Numbers are illustrative; agree your own.
The Sign-Off Table · thesignofftable.com/academy/sap-pow-203

Two things make these criteria work. They are numeric or binary wherever possible: 100% executed, 0 critical open. And entry criteria are enforced. Starting UAT before integration has exited means business users find integration defects, which wastes their time and their goodwill.

Entry criteria also cover the environment, not just the previous phase. Before integration testing at Contoso, Priya checks that the QAS client 100 has the right transports, that interfaces to the bank and the carrier are connected to test endpoints, that migrated master data from the latest mock load is present, and that testers have the business roles they will have in production. A missing role or a stale data load can invalidate days of testing, so these checks are worth the hour they take.

Exit criteria should also say what happens to the test assets: test cases and results saved, defects linked, and the regression candidates marked. That turns each phase into input for the next release, not just a hurdle for this one.

Severity definitions

Exit criteria about defects only work if everyone uses the same severity scale. Agree it in the test strategy:

SeverityDefinitionContoso example
CriticalProcess cannot run; no workaround; or legal or financial misstatementBilling posts revenue to the wrong company code
HighMajor function fails; workaround is costly or riskyCredit block does not trigger for one customer group
MediumFunction fails; reasonable workaround existsDelivery note prints without the customer PO number
LowCosmetic or minor inconvenienceA field label is misspelled on a custom form

A shared severity scale.

What would you do?

Contoso's integration test is 85% executed, but the program wants to start UAT next Monday as planned. What is the best course?

Key points
  • Every test phase has entry and exit criteria; a gate is the decision to move on.
  • In SAP Activate, most testing is in Realize; regression continues in Run.
  • Make criteria numeric or binary and enforce entry criteria.
  • Agree a shared severity scale so defect-based exit criteria mean the same thing to everyone.

Check your understanding · not graded

Lesson check

  1. 1. What do entry criteria describe?

  2. 2. In SAP Activate, in which phase does most testing take place?

  3. 3. Why enforce integration exit before UAT entry?

  4. 4. Which defect fits the critical severity definition?