Lesson 4 of 6

Results analysis and settlement

10 min

Listen to this lesson

0:00 / 7:44

At period-end, a project must answer two questions. For a customer project: how much revenue and margin has been earned so far? That is results analysis (or, in newer designs, event-based revenue recognition). For every project: where do the costs go? That is settlement. Results analysis runs first, because settlement moves its results too.

Results analysis on the customer project

CMC-GLF-240 is a fixed-price contract of USD 600,000 with planned costs of USD 450,000 (illustrative). By the end of period 6, actual costs are USD 180,000 and Great Lakes has been billed USD 150,000 at the first milestone. Results analysis with a cost-based percentage-of-completion method calculates progress as 180,000 ÷ 450,000 = 40%, so earned revenue is 40% × 600,000 = USD 240,000. Revenue billed is only USD 150,000, so results analysis posts USD 90,000 of revenue in excess of billings (accrued revenue) and the project shows a margin of USD 60,000 at 25%, as planned.

Item (period 6, illustrative)USD
Contract price600,000.00
Planned costs450,000.00
Actual costs to date180,000.00
Percentage of completion (cost-based)40%
Earned revenue240,000.00
Billed revenue150,000.00
Revenue in excess of billings (posted by settlement)90,000.00
Margin to date60,000.00

Results analysis for the Great Lakes program at the end of period 6.

Results analysis is configured through a results analysis key on the billing element and a results analysis version, with valuation methods and line IDs that group cost elements. It calculates values in controlling; the postings to the general ledger happen when the project is settled. Run it individually with KKA2 or collectively with KKAJ.

Settlement

Each WBS element that collects costs needs a settlement rule: one or more receivers with percentages or amounts, defaulted from the settlement profile. Toledo's elements settle periodically to their asset under construction; at completion, the AuC is capitalized to final assets. Costs that cannot be capitalized, such as staff training on the new warehouse system, settle to cost center 18101101 Toledo Distribution. The customer project settles its results analysis values to profitability: revenue, cost of sales and the WIP or accrual postings.

Settlement of the Toledo project: periodic to the AuC, part to expense, and final settlement to fixed assets.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306
  1. Post all period costsInvoices, confirmations, goods issues posted to the WBS elements
  2. OverheadOverhead surcharges calculated (CJ45 collective)
  3. Results analysisCustomer projects only (KKAJ)
  4. SettlementPeriodic settlement (CJ8G collective, CJ88 individual)
  5. CheckWBS elements show zero balance after settlement; receivers received the amounts
The project period-end sequence.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306
ReceiverWhenToledo / Great Lakes example
Asset under constructionPeriodic settlement of capital projectsCMC-TOL-DC.1 and .2, 100%
Fixed assetFinal settlement at completionBuilding, racking, IT assets
Cost centerNon-capitalizable costsTraining share of .3 to 18101101
Profitability segmentCustomer projectsGreat Lakes revenue, cost of sales, accrual

Settlement receivers used in this course.

What would you do?

Settlement of the Toledo project in period 6 fails for CMC-TOL-DC.3 with "settlement rule missing". The other elements settled. What should happen?

Results analysis calculates; settlement posts its values to the general ledger and profitability.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306

What goes wrong in testing

SymptomCauseTest
Customer project shows full revenue, no accrualResults analysis did not run before settlementRun the sequence in order and check RA values first
RA calculates zero progressPlanned costs missing for the results analysis versionCheck the plan version that RA reads before running
AuC receives too muchSettlement rule percentages exceed 100% across receiversCheck rules sum to 100% per element and period
Settlement posts to wrong accountSettlement cost element or allocation structure wrongReconcile settlement documents by G/L account

Results analysis and settlement defects.

  • Settlement period and posting period differ: settling period 6 while the fiscal period is still open for late invoices means late costs stay on the element until period 7.
  • Final settlement is run before all invoices for the AuC have arrived, so later invoices land on a completed asset project and need special handling.
  • A project type is switched from results analysis to EBRR without a cut-over plan for open projects, so the same contract shows revenue calculated two different ways.

A useful habit: before running any period-end step, write the expected numbers in the test case. For the Great Lakes program, that means 40% progress, USD 240,000 earned revenue, USD 90,000 accrual and USD 60,000 margin. For Toledo, the exact amount each AuC and the cost center should receive. If the system matches the numbers you wrote down beforehand, the test passes for a reason; if you write them afterwards, you are only describing what happened.

Key points
  • Results analysis calculates earned revenue and WIP; settlement posts them.
  • Cost-based POC: progress = actual cost ÷ planned cost; earned revenue = progress × contract price.
  • Capital projects settle periodically to AuCs and finally to fixed assets.
  • Run overhead, results analysis and settlement in that order.

Check your understanding · not graded

Lesson check

  1. 1. Planned costs USD 450,000, actual USD 180,000, price USD 600,000, cost-based POC. What is earned revenue?

  2. 2. When do results analysis values reach the general ledger?

  3. 3. Where do periodic settlements of a capital WBS element usually go?

  4. 4. Which step must run before settlement at period-end?