Lesson 1 of 6

Projects in SAP S/4HANA

10 min

Listen to this lesson

0:00 / 8:25

Some work does not fit a cost center or an internal order: a new distribution center, a customer development contract, a plant rebuild. It has phases, dates, a budget that someone approved, many people posting to it, and a result that must end up somewhere, as an asset, an expense or a margin. SAP's Project System (PS) handles that work, and it is still part of SAP S/4HANA Private Edition and on-premise. This course teaches it the way a controller and a tester need it: structure, money, period-end and proof.

sap-co-202 drew the line at Contoso Motor Co.: internal orders for measures one cost center manager owns that finish within a year, and projects for anything that needs a work breakdown, such as the new Toledo distribution center. This course picks up that project, plus one customer project, and follows both through a year.

Contoso's two projects (illustrative course data)

ProjectTypeCompany codeMoneyWhere costs end up
CMC-TOL-DC Toledo distribution centerCapital (investment) project1810 Contoso Parts DistributionBudget USD 4,000,000Assets under construction, then fixed assets; some expense to 18101101 Toledo Distribution
CMC-GLF-240 Great Lakes 24 V programCustomer project1710 Contoso Motor Co.Fixed price USD 600,000Revenue and cost of sales on the project, via results analysis or event-based revenue recognition

The two projects used throughout this course.

The building blocks

Project definitionThe frame: company code, controlling area A000, profit center, project profile, dates
WBS elementsThe work breakdown structure: a hierarchy of tasks that carry costs, budget and revenue
Networks and activitiesThe how and when: activities with durations, work, materials and relationships
MilestonesEvents that trigger billing, progress or reporting
A project in SAP S/4HANA, from frame to schedule.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306

The project definition holds defaults for everything below it. WBS elements are the controlling objects: costs post to them, budgets sit on them, settlement rules move their costs on. Networks are the logistics side: activities that plan dates, internal work by work center, external services and material components, each of which generates planned costs on the WBS element it belongs to. Small projects often use WBS elements only; projects with real scheduling use both.

How the project objects relate: WBS elements form a hierarchy, carry settlement rules, and own network activities.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306

Where projects sit in finance

Every posting to a WBS element is a line in the Universal Journal (ACDOCA) with the WBS element as account assignment, so project costs, revenues and settlements appear in the same ledger as everything else. Plan values go to ACDOCP. A WBS element carries a profit center, which is how project results reach margin and segment reporting. For a capital project, the WBS element is also an investment measure linked to an asset under construction, which connects PS to asset accounting (sap-fin-205).

Costs collect on WBS elements and leave them only by settlement, to an asset under construction or a cost center.
The Sign-Off Table · thesignofftable.com/academy/sap-co-306

Transactions and apps you will use

TaskSAP GUINotes
Create and change projectsCJ20N Project BuilderStructure, dates, assignments in one screen
Structure overview reportCN41NProject structure with key fields and statuses
Overall cost planningCJ40Plan by WBS element and year
BudgetCJ30, CJ32Original budget, release
SettlementCJ88, CJ8GIndividual and collective settlement
Results analysisKKA2, KKAJIndividual and collective processing

Classic PS transactions used in this course. Fiori apps exist for many of these tasks; check the Fiori apps library for your release.

What would you do?

Contoso wants to track the cost of a two-day dealer training event in Chicago, approved by one cost center manager, finished within the month. A colleague suggests a project with three WBS elements. What do you recommend?

What goes wrong in testing

SymptomUsual causeTest
Project costs show in the wrong margin reportWBS element profit center defaulted wrongly from the project definitionCheck profit center on every WBS element after creation
Postings to a WBS element failElement is not an account assignment element or not releasedPost a test invoice to each level of the hierarchy
Capital costs never reach assetsNo investment profile or AuC on the WBS elementFollow one cost from posting to AuC

Structure defects that surface only when money moves.

Profiles: the hidden configuration

Most project behavior is not visible on the project screen; it comes from profiles chosen when the project is created. The project profile sets defaults for organizational units, the budget profile, the planning profile, the settlement profile and the investment profile. The network profile controls how networks schedule and cost. The status profile adds user statuses. Choosing the wrong project profile at creation, for example the overhead profile for a capital project, produces a project that looks right and behaves wrongly: no AuC, wrong settlement receivers, no availability control.

ProfileControlsWhat to check in a test
Project profileDefaults for the whole project and which other profiles applyEach project type uses its own profile
Budget profileBudget values, currency, availability control activationCapital projects activate AVC; overhead projects as designed
Settlement profileAllowed receivers, settlement cost elements, document typeReceivers allowed match the design (AuC, cost center, profitability)
Investment profileCreation of an AuC for capital WBS elementsReleased capital elements have an AuC
Results analysis keyHow customer project results are calculatedCustomer billing elements carry the right key

Profiles that decide project behavior, and the test that catches a wrong one.

Contoso keeps three project types after the conversion: capital, customer and overhead. Each has its own project profile, and the test set includes one new project of each type created from scratch, so the profiles themselves are tested, not only converted projects that already carry their settings.

Key points
  • Project System remains part of SAP S/4HANA Private Edition and on-premise.
  • Project definition, WBS elements, networks and milestones are the building blocks.
  • WBS elements are the controlling objects; postings land in the Universal Journal.
  • Costs leave a WBS element only through settlement.

Check your understanding · not graded

Lesson check

  1. 1. Which project object carries costs, budget and settlement rules?

  2. 2. When is a project preferable to an internal order at Contoso?

  3. 3. Where do project postings appear in SAP S/4HANA?

  4. 4. What links a capital project to asset accounting?