The Sign-Off Table

Lesson 5 of 5

Go-live sign-off sequence

10 min

The go-live decision is not one signature. It is a sequence of sign-offs, each resting on the one before it: technical readiness, data, functional verification, finance, and finally the business decision to open the doors. If you collapse them into one meeting, people sign things they have not checked. If you sequence them, each signer is accountable for a specific, evidenced statement.

The sequence

1. Technical readinessBasis and platform: system up, backups taken, transports imported, jobs scheduled, interfaces connected, monitoring on.
2. Data readinessData owners: loads complete, technical and business reconciliations signed, known errors accepted or fixed.
3. Functional verificationTest lead and key users: PVT set passed, failures triaged, workarounds documented.
4. Finance and controlsFinance process owner: balances and open items reconcile; period and posting controls in place.
5. Security and accessSecurity lead: user roles assigned, emergency access arranged, test users locked.
6. Go/no-go decisionSteering committee: decides against the acceptance criteria and residual risks.
7. Business releaseBusiness leaders: users unlocked, communications sent, hypercare starts.
Each layer rests on the one below. A later signer relies on, but does not re-check, the earlier ones.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-309

Acceptance criteria, agreed in advance

SAP's onboarding guidance describes go-live acceptance criteria as predefined conditions that must be met before the new solution launches, and gives examples such as an acceptable pass rate for integration and user acceptance tests, completed end-user training, no critical open issues, and validated migrated data. Write your criteria before the dress rehearsal and test them during it, so that on the night nobody is inventing thresholds under pressure.

CriterionContoso thresholdEvidence
PVT resultAll critical checks passed; no open priority 1 defectsPVT test plan status and defect list
Data reconciliationGL balances for company code 1710 match legacy to the cent; inventory variances within agreed toleranceSigned reconciliation reports
Open defectsNo priority 1; priority 2 only with documented workaround and ownerDefect report with workarounds
FallbackFallback still possible until the agreed point of no returnCutover timeline and decision log
ReadinessHypercare team staffed, users trained, support process liveReadiness checklist

Contoso's go-live acceptance criteria. Thresholds are agreed by the steering committee before the dress rehearsal.

Running the go/no-go meeting

  1. Grace (PMO lead) chairs; Luis presents cutover status and timings against plan.
  2. Each earlier signer confirms their sign-off and states any conditions.
  3. Priya presents PVT results, open defects with severity and workarounds, and the residual risk.
  4. The group checks each acceptance criterion: met, met with conditions, or not met.
  5. The decision is recorded: go, go with conditions (each with an owner and due date), or no-go with the fallback path.
  6. The decision log is stored with the evidence, and the business release step starts.
  1. Are all acceptance criteria met?Yes → go; start business release · No → next question
  2. Do the gaps have accepted workarounds, owners and due dates?Yes → go with conditions, each recorded in the decision log · No → next question
  3. Is the point of no return still ahead?Yes → no-go; run the fallback path · No → escalate to the sponsor and fix forward under hypercare
The go/no-go meeting ends in one of three recorded outcomes: go, go with conditions, or no-go.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-309

After the decision: release and the final lessons

Who signs technical readiness in the cloud

On SAP S/4HANA Cloud Private Edition under RISE, some technical cutover steps (system provisioning, backups, restores, certain transports) are performed by SAP or the hosting provider under the contract, not by Contoso's own Basis team. Technical readiness then rests partly on the provider's confirmation. Agree in advance what the provider will confirm, in what form and by when, and put those confirmations in the runbook as checkpoints. In SAP S/4HANA Cloud Public Edition even more of the technical layer is SAP's, but data, functional, finance and business sign-offs remain the customer's responsibility.

Sign-offPrivate Edition (RISE)Public Edition
Technical readinessShared: provider confirms provisioning, backups and some transports; Contoso's Basis team the restMostly SAP
Data readinessCustomerCustomer
Functional verificationCustomerCustomer
FinanceCustomerCustomer
Go/no-go and business releaseCustomerCustomer
In the cloud the provider takes on more of the technical layer, but every business sign-off stays with the customer.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-309

Business release is a step of its own: unlock users in the agreed sequence, send the go-live message, start hypercare and switch on first-transaction monitoring. Then, within a week of go-live, hold a final cutover retrospective. Some of what you learn will help the next wave or the next company code roll-out; record it against the runbook task IDs so the runbook becomes a reusable asset, not a one-off spreadsheet.

What would you do?

At Contoso's go/no-go meeting, all criteria are met except one: a priority 2 defect in delivery output for plant 1720 Chicago has a manual workaround but no fix yet. The plant manager wants to go live. What should the group decide?

Key points
  • Go-live sign-off is a sequence: technical, data, functional, finance, security, go/no-go, business release.
  • Agree acceptance criteria and thresholds before the dress rehearsal, and test them during it.
  • Every sign-off states what is approved, the evidence and the residual risks accepted.
  • Record the decision and any conditions with owners and dates, then capture final lessons into the runbook.

Check your understanding · not graded

Lesson check

  1. 1. Which sign-off normally comes first in the go-live sequence?

  2. 2. When should go-live acceptance criteria be agreed?

  3. 3. What turns a signature into a real sign-off?

  4. 4. What does "go with conditions" require?