Lesson 5 of 6

Capacity planning

9 min

Listen to this lesson

0:00 / 6:25

A TCoE serves three kinds of demand at once: SAP release events on a calendar, projects such as roll-outs, and a steady stream of enhancements and fixes. Each has its own peaks, and they collide. Capacity planning is how the TCoE sees a collision three months ahead instead of three days ahead.

Supply: three pools

PoolContoso sizeMonthly capacity (planning value)Lead time to change
TCoE core5 peopleAbout 650 hours (5 × 130)Months: hiring
Business test network12 key users plus MonterreyBooked per event; typically 200–400 hours in a regression monthA quarter: line manager agreement
Partner call-offFramework agreementUp to 1,000 hours a month4 weeks' notice under the agreement

Three supply pools. Each has a different lead time, which is why the plan must look at least a quarter ahead.

Plan the core to about 80% of its theoretical capacity. The remaining 20% absorbs emergency fixes, sickness and the meetings nobody plans. A core planned at 100% is late on everything by the second month.

Demand: three streams

  • Calendar demand: feature pack stack updates, SAP Notes and patch checks, year-end regression. Known months ahead from the TCoE calendar in sap-tst-401.
  • Project demand: roll-outs, new modules, integration changes. Known from the project portfolio, usually with dates that slip.
  • Flow demand: about 120 enhancements a year, plus fixes. Forecast as an average per month with a range.

A worked month

In Contoso's plan, November is the collision month: the next feature pack stack update falls in the same month as Wave 2 system integration testing for company code 1910, and enhancements keep arriving.

November demandHoursSupplyHours
Feature pack stack regression (700 h per event)700TCoE core at 80%520
Wave 2 SIT for company code 1910900Business test network (booked)300
Enhancements (10 a month at 22 h)220Partner call-off (to be ordered)1,000
Total1,820Total1,820

Contoso's November plan. The partner call-off must be ordered by early October because of its four-week notice.

Back-scheduling supply: key users are booked a quarter ahead and partner call-off ordered four weeks ahead of the collision.
The Sign-Off Table · thesignofftable.com/academy/sap-tcoe-402

Hypercare overlaps

After any go-live, including Wave 2, the same people who tested are needed in hypercare to reproduce production incidents. Treat hypercare as demand on the plan, at least for the test architects and the key users of the affected processes, for four to six weeks. A common failure is to plan the next release regression in the same weeks, using the same key users who are now fighting incidents.

Key-user capacity is per process, not per head

Twelve key users is not one pool of twelve. Each is expert in one or two processes, and a regression month needs the right ones. Plan key-user supply per process, with the dates each person is unavailable, and agree the rules with line managers once a year instead of negotiating every booking.

ProcessNamed key usersNever availableBooking rule
Order to cash3, including MariaSpring fleet-ordering peakBooked a quarter ahead; at most 30% of their week
Record to report3 from Dan's teamMonth-end and quarter-end close weeksNever in close weeks; year-end needs CFO approval
Procure to pay3, including Ana and OmarPayment run daysBooked a quarter ahead
Plan to produce2 in Detroit, 1 in ChicagoPlant shutdown weeksCoordinated with the plant manager
Order to cash, company code 1910Monterrey groupMexican fiscal deadlinesThrough the Monterrey test coordinator

Key-user supply by process at Contoso. Counts and names not used elsewhere are illustrative.

Options when demand exceeds supply

  1. Can the project date move without business harm?Yes → move it and record who agreed · No → next question
  2. Can partner capacity arrive in time under the call-off notice?Yes → order it now · No → next question
  3. Can regression scope be reduced safely through release assessment?Yes → reduce, with the residual risk accepted by the owner · No → next question
  4. None of the above?Escalate to the quality council with options, costs and risks
When demand exceeds supply, work through options in order, and never cut coverage silently.
The Sign-Off Table · thesignofftable.com/academy/sap-tcoe-402
  1. MonthlyRolling 3-month planDemand and supply per pool; collisions flagged
  2. QuarterlyQuality councilNext two quarters reviewed; partner and key-user bookings confirmed
  3. AnnuallyBudget and calendarCore size, call-off volume and the next year's TCoE calendar
The planning rhythm. Each horizon matches the lead time of the pool it controls.
The Sign-Off Table · thesignofftable.com/academy/sap-tcoe-402

What would you do?

Grace adds a new warehouse project to November. Priya's rolling plan shows November demand now 400 hours above supply, and the partner call-off notice period has already passed. What should Priya do?

Key points
  • Plan three supply pools (core, business network, partner call-off) with their different lead times.
  • Plan the core at about 80% so emergencies and absences do not make everything late.
  • Forecast calendar, project and flow demand; treat hypercare as demand too.
  • Use a rolling three-month plan; order call-off and book key users before collisions arrive.
  • When demand exceeds supply, present options with cost and risk; never cut coverage silently.

Check your understanding · not graded

Lesson check

  1. 1. Why plan the TCoE core at about 80% of its capacity?

  2. 2. Contoso's partner call-off needs four weeks' notice. When should Priya order it for a November collision?

  3. 3. Why treat hypercare as demand in the capacity plan?

  4. 4. Demand exceeds supply and no capacity can be added. What should the TCoE never do?