Testing planning results: tolerances and parallel runs

10 min

Listen to this lesson

0:00 / 7:18

A goods movement has one correct result. A planning run does not. Two planning engines given the same inputs produce different forecasts and supply plans because they use different algorithms, buckets and rounding. Even the same engine can give a different result after a release upgrade. So planning tests compare outputs with tolerances, explain every difference outside them, and use parallel runs where old and new systems plan the same period from the same data.

Designing a parallel run

  1. Freeze the inputs. Take the history, stock, open orders and master data at one cut-off (Contoso: month-end, 18:00) and load the same snapshot into APO and IBP.
  2. Align settings that should be equal. Horizons, buckets, units, calendars and lanes; differences here are setup errors, not results.
  3. Run both cycles. APO DP and SNP as usual; IBP forecast, consensus and supply heuristic as designed.
  4. Compare at agreed levels. Network total, plant, product family, then top products; never cell by cell first.
  5. Classify every difference outside tolerance. Input difference, design change, engine difference or defect.
  6. Review with planners. Sunita and Jonas accept, reject or ask for analysis; decisions are logged.
Parallel run logic: one snapshot, two engines, a comparison by level, and every exception classified.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301

Setting tolerances

Tolerances are business decisions, set with planners before the first run and written into the test plan. They tighten at higher levels, because errors cancel out in totals and because aggregate numbers drive S&OP decisions.

Key figure and levelTolerance (illustrative)Rationale
Released demand, network total per month±1%Drives S&OP and finance; must reconcile closely
Consensus demand, plant per month±3%Capacity decisions are taken per plant
Statistical forecast, product family per month±5%Model differences expected; families matter for S&OP
Statistical forecast, top 20 products per month±10% or explainedSingle products vary most; explain every miss
Supply split Toledo, Detroit share±3 percentage pointsContract and capacity commitments
Capacity load ASSY-10, per month±2%Overload decisions depend on it
Forecast accuracy (weighted MAPE), last 12 monthsIBP no worse than APO by more than 1 pointThe new model must not be worse

Contoso's tolerance table for the planning parallel runs.

Worked example: the March parallel run

Released demand for CMC-ALT-100, network total, March: APO 9,840, IBP 9,910, a difference of 70 or 0.7%, inside ±1%. At plant level, Detroit: APO 6,880, IBP 7,150, +3.9%, outside ±3%. Drilling down, aftermarket demand explains +230 of the +270: APO's history included credit memos as negative quantities in two months, IBP's did not. Sunita classifies it as an input difference that favors IBP, because IBP uses the agreed, cleaner history. She accepts with reason code "history correction". The remaining +40 is within the product-level tolerance.

LevelAPOIBPDifferenceResult
Network, March9,8409,910+0.7%Within ±1%
Detroit, March6,8807,150+3.9%Outside ±3%: classified
Detroit aftermarket1,7702,000+13.0%History correction, accepted
Chicago, March2,9602,760−6.8%Outside: under analysis

Illustrative course data: March comparison and its classification.

Two parallel cycles per stage, staggered so demand is proven before supply relies on it.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301
Difference classExample at ContosoAction
Input differenceCredit memos in APO historyFix the load or accept the cleaner source
Design changeToledo split now set by lane quotaPlanner accepts with reason
Engine differenceIBP heuristic buckets monthly, APO weeklyExplain; tune if material
DefectChicago capacity loaded in hours, not piecesRaise, fix, rerun
Four classes of difference; only one of them is a defect.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301

Testing PP/DS by shadow scheduling

Detailed schedules cannot be compared with simple percentages. Contoso ran shadow scheduling for ASSY-10: for six weeks, the Detroit scheduler scheduled in APO as usual, while the same orders were scheduled in embedded PP/DS in the test system from the same snapshot. The comparison used measures that matter on the shop floor: number of late orders, total setup time, load per shift, and how many orders the scheduler had to move by hand. Tolerances were set per measure, for example no more late orders than APO and setup time within 5%.

Measure (ASSY-10, week 3)APOEmbedded PP/DSToleranceResult
Late orders21No more than APOPass
Total setup time (hours)14.014.5±5%Pass (+3.6%)
Max load per shift96%101%≤100%Fail: overload on Thursday late shift
Orders moved by hand69No more than APOFail: under analysis

Illustrative course data: shadow scheduling results for one week.

The Thursday overload turned out to be a defect: the resource's shift calendar in S/4HANA lacked a planned maintenance break that APO had in its own resource. That is a typical finding, because embedded PP/DS reads master data from S/4HANA directly, so S/4HANA master data quality now decides scheduling quality.

What would you do?

Chicago is −6.8% in the March comparison, outside the ±3% tolerance. Jonas suspects IBP is right because Chicago lost a customer. What should Priya do?

Key points
  • Planning outputs differ by design; compare with tolerances, not exact values.
  • Freeze one snapshot for both systems and record its timestamp.
  • Compare top down: network, plant, family, product.
  • Classify every exception: input difference, design change, engine difference or defect.

Check your understanding · not graded

Lesson check

  1. 1. Why are tolerances tighter at the network level than at product level?

  2. 2. What is the first step of a parallel run?

  3. 3. Detroit is +3.9% because APO history included credit memos. How is this classified?

  4. 4. A difference is outside tolerance. What does that mean?

  5. 5. Chicago capacity was loaded in hours instead of pieces. Which class is it?