Mapping DP, SNP and PP/DS to their successors

10 min

Listen to this lesson

0:00 / 7:43

Mapping APO to its successors is a function-by-function exercise. The names look similar (forecast, heuristic, product view), but the data models differ, and so do the places where the result lands in S/4HANA. A good mapping table names the APO function, the successor function, the gap and the test that proves the successor.

APO functionSuccessorNotes for the test team
DP statistical forecast and planning booksIBP for demand: forecast models, planning viewsRebuilt as key figures and models; compare forecasts in parallel
DP release to ERP (PIRs)IBP release via CI-DS to PIRsVersion and date mapping of PIRs change
SNP heuristicIBP time-series supply planning heuristicAggregate buckets; check propagation and lanes
SNP optimizer and CTMIBP supply planning optimizer; order-based planningDifferent engines; expect different but explainable results
SNP deployment and transport load builderIBP deployment functions or S/4HANA processesCheck availability in your IBP release
PP/DS heuristics and DS planning boardEmbedded PP/DS in S/4HANASame concepts; master data now comes from S/4HANA directly
gATPaATP in S/4HANAFit-gap first; rule-based substitution needs special checks
SNC (supplier collaboration)SAP Business Network supply chain collaborationOut of scope at Contoso

APO functions and their successors, with the test angle for each.

The successor map: two functions move to the IBP cloud tenant, two move into the S/4HANA core.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301

Embedded PP/DS in S/4HANA

PP/DS has been part of S/4HANA since release 1610, delivered through business function SCM_PPDS_ON_ERP. Using it requires the Advanced Planning and Scheduling switch in Customizing (Advanced Planning > Basic Settings > Activate Advanced Planning and Scheduling), and that switch needs a separate license (SAP names it S/4HANA Manufacturing for planning and scheduling; check your contract). Materials are made relevant through the Advanced Planning view of the material master. Production data structures (PDS) are generated from production versions, BOMs and routings; transaction CURTOADV_CRT creates them. The familiar tools remain: product view /SAPAPO/RRP3, the detailed scheduling planning board, plus Fiori apps for scheduling.

In embedded PP/DS the PDS is derived from S/4HANA's production version, BOM and routing, and work centers become PP/DS resources.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301

Two Contoso facts make this concrete. First, the conversion generated production versions for about 300 materials that had none in ECC; PP/DS needs them, so their quality now matters for scheduling. Second, CIF does not disappear completely in embedded PP/DS: some objects still use integration models (CFM1 to create, CFM2 to activate), while others transfer directly when a material is advanced-planning-relevant. Treat every CIF model and user exit from SP1 as a line item to analyze, not as something that "goes away".

Worked example: Contoso's mapping for CMC-ALT-100 in Detroit

Today (APO SP1)TargetProof
DP forecast at product / location / customer group, monthlyIBP consensus demand at the same levelForecast parallel run within tolerance
DP release to ERP as PIRs, version 00IBP release via CI-DS to PIRs, version 00Counts, totals, sampled dates
SNP heuristic: Toledo demand sourced 70% Detroit, 30% ChicagoIBP transportation lanes with the same quotaSupply split within tolerance
PP/DS heuristic and planning board on ASSY-10Embedded PP/DS on resource from ASSY-10Sequence and load per shift compared
gATP product check on sales ordersaATP product availability checkConfirmed dates on a fixed order set

Illustrative course data: one product's mapping and the evidence each line needs.

Gaps worth checking in your release

Successor products have grown fast, and some gaps that blocked early projects have closed. Others remain. Do not rely on a blog from 2017 or 2020; check SAP's current documentation and roadmap for your IBP release and S/4HANA release, and run a fit-gap with your own data. Typical items to check:

  • Deployment and transport load building after SNP: which IBP release supports the deployment logic you need, or does S/4HANA MRP with stock transfers cover it?
  • Capable-to-match (CTM) rules: map them to IBP order-based planning or to supply optimizer constraints, and test priorities explicitly.
  • Rule-based ATP and substitution from gATP: check the aATP features in S/4HANA 2025 (for example product allocation and alternative-based confirmation) against each rule.
  • Characteristic-dependent planning for configurable products such as CMC-ALT-240: confirm how embedded PP/DS handles the configuration.
  • Planning book reports used for management: rebuild as IBP views, dashboards or analytics, not as custom code.
  1. Name the functionAPO function and the decision it supports
  2. Find the successorIBP, embedded PP/DS or aATP feature in your release
  3. Run fit-gap with dataContoso products, plants and real volumes
  4. Classify the gapStandard covers it, configure, extend, or accept a process change
  5. Write the proofThe test that shows the successor supports the decision
The fit-gap routine for each mapped function.
The Sign-Off Table · thesignofftable.com/academy/sap-scm-301

At Contoso, the fit-gap closed with three real gaps: a customer-priority rule in gATP that needed aATP product allocation, a Toledo deployment report that became an IBP view, and a PP/DS sequencing rule for winding wire changeovers on WIND-10 that needed a setup matrix. Each became a design item with a named test.

What would you do?

Kenji's team finds 14 CIF user exits on SP1. A consultant says embedded PP/DS "has no CIF", so the exits can be ignored. What should Theo do?

Key points
  • DP and SNP map to IBP; PP/DS and gATP map into S/4HANA.
  • Embedded PP/DS needs the advanced planning switch (licensed), the Advanced Planning material view and PDS from production versions.
  • CIF and user exits need line-by-line analysis; they do not simply vanish.
  • Test each mapped rule at its limits, not only on typical data.

Check your understanding · not graded

Lesson check

  1. 1. Which transaction creates production data structures for embedded PP/DS?

  2. 2. Where is a material made relevant for embedded PP/DS?

  3. 3. What is the successor of APO gATP?

  4. 4. Why did Chicago receive 45% of Toledo demand in the first IBP build?