What SAP Readiness Check is for

11 min

Listen to this lesson

0:00 / 9:23

SAP Readiness Check is a self-service analysis that SAP offers at no additional cost to customers with an active maintenance agreement. You collect data in an existing system, upload it, and SAP returns an interactive dashboard that shows what a transition will involve. For a system conversion from SAP ERP 6.0 to SAP S/4HANA, the relevant scenario is SAP Readiness Check for SAP S/4HANA, governed by central SAP Note 2913617. Contoso uses it to understand what converting its ECC 6.0 EHP 8 production system EP1 will take.

Readiness Check has grown well beyond its first purpose. SAP's user group material from November 2025 lists nine supported scenarios, including SAP S/4HANA conversion, SAP S/4HANA upgrades, SAP BW/4HANA conversion and SAP ERP usage and data profiling. This course covers only the SAP S/4HANA conversion scenario.

What it analyzes

CheckWhat it tells you
Simplification ItemsWhich of SAP's documented changes are relevant for your system, with effort ranking
Compatibility Scope AnalysisItems tied to compatibility packages and whether an alternative exists or is planned
Activities Related to Simplification ItemsMandatory, conditional and optional activities by conversion phase
Add-On CompatibilityWhether installed add-ons are compatible with the target release
Active Business FunctionsWhether active business functions are compatible or would block the conversion
SAP S/4HANA SizingEstimated memory and disk, top tables and data volume management potential
Custom Code AnalysisResults of custom code checks grouped by simplification item category
IntegrationInterface inventory and the interfaces most likely to be impacted
Customer Vendor Integration AnalysisBusiness partner synchronization status and data quality issues
Planned Downtime CalculatorExpected business downtime for a standard conversion
Financial Data QualityInconsistencies in general ledger, asset accounting and material ledger data
SAP Business AI CapabilitiesSAP Business AI capabilities and their readiness against the selected Private Edition target release
App Availability, Recommended SAP Fiori AppsWhich used transactions and apps change, and which Fiori apps fit your usage
SAP Innovative Business SolutionsCustom developments SAP built for your customer number that must be checked for SAP S/4HANA
Business Process Discovery and othersProcess key figures, backlog of old open documents, innovation potential

Checks in SAP Readiness Check for SAP S/4HANA, as listed in SAP's Key Feature Overview (October 2026). The list grows over time.

The Readiness Check tiles grouped by what they tell you: functional change, technical blockers, code and interfaces, data quality, and users.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-201
SAP Readiness CheckSimplification Item Check
TypeCloud-based self-service with a dashboardReport /SDF/RC_START_CHECK in SAP GUI
ScopeSimplification items plus add-ons, business functions, custom code, sizing, integration and moreSimplification item relevance and consistency
Called by Software Update ManagerNoYes
MandatoryNo, but highly recommendedYes
Main usePlanning and trackingOperational cleanup up to downtime
Readiness Check and the Simplification Item Check serve different purposes; SAP says both are required.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-201

When to run it

SAP recommends running it very early, in the Discover phase or at the start of Prepare, to find mandatory preparation steps, and repeating it as the conversion date approaches to track progress. It is most useful before budgets and timelines are fixed: an incompatible business function or a large financial data cleanup found after the plan is approved becomes a change request rather than a planning input.

  1. DiscoverFirst analysis on EP1Scope, effort drivers and blockers before the business case
  2. PreparePlanning baselineFindings become workstream tasks in SAP Cloud ALM
  3. Before mock 1Progress checkRepeat to confirm consistency errors and CVI progress
  4. Before mock 2Final readinessRepeat again; remaining items owned and scheduled
When Contoso runs Readiness Check across the program.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-201

Where the results live

Results are available in two environments: SAP for Me (quick link me.sap.com/readinesscheck), for all customers with an active maintenance agreement, and SAP Cloud ALM, for customers with a tenant (SAP Note 3344480 describes the deployment options). In SAP for Me you can also ask Joule how to reach the tool. Contoso runs its S/4HANA program in SAP Cloud ALM, so Grace's team creates the analysis there and links findings to the project. A point-in-time report can be generated for offline review, and the dashboard's "Learn More" side panel holds SAP's documentation for each check.

From production to plan: Sam collects the data in EP1, the analysis lives in SAP Cloud ALM, and Grace’s PMO turns findings into project follow-ups.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-201

Worked example: what Contoso's first analysis said

TileEP1 result (illustrative course data)What the program decided
Simplification Items118 relevant, 9 ranked highEach high item assigned to a workstream lead
Custom Code Analysis11,800 Z objects, about 40% unusedDelete unused code; 7,500 objects in scope
Customer Vendor Integration4,850 customers with no business partner yetCVI pre-project started at once
Add-On CompatibilityOne third-party add-on with unknown statusSam asks the vendor for a written statement
IntegrationIDocs, RFCs and web services, many through Process OrchestrationTheo's team checks each impacted interface
Planned Downtime CalculatorClose to the 60-hour windowArchiving before Mock 1; DMO tuning in the mocks
Financial Data QualityInconsistencies in several fiscal yearsDan's team corrects them before the finance migration

The first EP1 analysis in one table: each tile becomes a decision with an owner.

Notice what the table does not contain: a verdict. Readiness Check never says "ready" or "not ready". It lists what has to happen and roughly how hard it is. The program decides whether the plan is affordable. Public Edition note: this scenario is for converting an existing SAP ERP system, so it applies to Private Edition and on-premise targets; a move to SAP S/4HANA Cloud Public Edition is a new implementation and uses other assessment tools.

What would you do?

Grace wants to skip Readiness Check because "the Simplification Item Check is mandatory anyway and gives us the same list". What should the solution architect say?

Key points
  • Self-service analysis of the source system; central SAP Note 2913617.
  • Covers simplification items, add-ons, business functions, sizing, custom code, integration, CVI, finance data and more.
  • A planning tool: run early, repeat to track progress.
  • Complements the mandatory Simplification Item Check; it does not replace it.

Check your understanding · not graded

Lesson check

  1. 1. Which SAP Note is the central note for SAP Readiness Check for SAP S/4HANA?

  2. 2. Which tool is called by Software Update Manager during the conversion?

  3. 3. When does SAP recommend running Readiness Check first?

  4. 4. Which statement about a green Readiness Check tile is correct?

  5. 5. Contoso's first analysis shows 4,850 customers without a business partner. Which tile shows this?