Lesson 4 of 5

Recording decisions and sign-off evidence

9 min

Six months after go-live, an auditor, a new CFO or a hypercare investigation asks: who decided this release could go, on what basis, and what did they know? If the answer is a set of slides and someone's memory, the program has a problem. A decision record makes the answer a five-minute lookup.

What a decision record contains

DecisionGo, go with conditions, or no-go; the release and scope it applies to
WhoDecision makers present, chair, absent decision makers and their delegates
EvidenceThe dated snapshots each criterion relied on, with their sources
Conditions and risksEach with owner, date, workaround and the person who accepted it
DissentAny decision maker who disagreed, and why
The five parts of a decision record.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-302

Evidence must be frozen. Cloud ALM analytics are live, so the defect count shown on Monday will differ by Thursday. For each criterion, keep the figure, the filter that produced it, the time and the person who took it. The SAP Cloud ALM quality gates course in this Academy covers how Contoso snapshots and stores gate evidence on Quality Gate tasks; the release board uses the same practice.

Where to keep it

RecordWhere Contoso keeps itWhy there
Board decision and conditionsQuality Gate task for the release in Cloud ALM, with checklist and attachmentsLives with the project; visible on the timeline
Accepted risks per featureNote on each affected feature and its defectsFound when someone looks at the feature later
Condition follow-upsLinked tasks with owner and due dateTracked to closure, not forgotten in minutes
Signed reconciliations and sign-off formsAttachments on the gate task, plus the controlled document storeRetention and audit access

Where each part of the decision lives.

The sign-off chain

  1. Criteria ownersEach states met, not met or conditional, with evidence
  2. Process ownersDan and Maria sign business readiness and accept risks
  3. Release managerLuis confirms build and deployment readiness
  4. BoardGrace records the decision and conditions
  5. SponsorConfirms go for a major release
Sign-offs flow upward; each layer relies on the evidence below it.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-302
Weak recordStrong record
"Release approved""Go with conditions for Release 1, all scope"
"Testing complete""SIT and UAT exit criteria met; snapshot Thursday 14:00, filter Release 1"
"Some open defects""Two high defects; risk statements attached; accepted by Dan and Maria"
"Team agreed""Decision makers: Dan, Maria, sponsor; chair Grace; dissent: none"
The same decision, recorded weakly and strongly.
The Sign-Off Table · thesignofftable.com/academy/sap-rel-302

Signatures should mean something specific. "Approved" on a slide means little. "I, Dan, accept that rebate accruals for one condition type will be posted manually until Release 1.1, using the documented workaround" means a lot. Write sign-off statements in that style; they take a minute longer and remove arguments later.

Delegation and absence

Decision makers get sick, travel and go on leave, usually in go-live week. Agree delegates in advance and record them in the decision record: "Dan absent; finance decisions delegated to the corporate controller by email dated Monday." A delegate who was never named in writing is a source of dispute later, especially when a risk they accepted turns into an incident.

  • Name a delegate for every decision maker before the board cycle starts.
  • Record the delegation, with its date and scope, in the decision record.
  • Delegates receive the same pre-read and have the same question window.
  • Keep records for the retention period your auditors and legal team set, beyond the life of the project workspace.

What would you do?

A week after go-live, someone edits the gate checklist in Cloud ALM to mark a condition as met that was actually still open at the time of the board. What is the issue and the fix?

Key points
  • A decision record holds the decision, who, frozen evidence, conditions and risks, and dissent.
  • Freeze evidence: figure, filter, time and author.
  • Keep decisions on the release’s Quality Gate task and risks on the affected features.
  • Write sign-off statements that say exactly what is accepted.

Check your understanding · not graded

Lesson check

  1. 1. Why must board evidence be frozen as snapshots?

  2. 2. Where should follow-up work for a condition be tracked?

  3. 3. Which sign-off statement is strongest?