Release Readiness and Sign-Off Governance
Course quiz
Release Readiness and Sign-Off Governance
Keep this: job aid
Release readiness and sign-off card
- Six dimensions: build, test, security, operations, data, business.
- Each criterion: measure, threshold, evidence source, owner; marked blocking or conditional in advance.
- Pre-read 24–48 hours ahead with dated snapshots; the meeting handles exceptions only.
- Presenters inform; process owners and sponsor decide.
- Open issues become risk statements: cause, impact, likelihood, workaround, owner, date.
- Outcomes: go, go with conditions, no-go. Likely and severe risks are rejected.
- Decision record: decision, who, frozen evidence, conditions, accepted risks, dissent.
- Keep it on the release’s Quality Gate task; risks on affected features; conditions as linked tasks.
- Post-release review: blameless, criteria versus reality, actions with owners, reported at the next board.