Lesson 4 of 5

Assessing defects by supply and inventory value impact

10 min

Listen to this lesson

0:00 / 7:13

A misaligned label on the production order print and an MRP run that creates no proposals for the rotor are both defects. Only one can stop the line. Plan-to-produce defects need a rating scheme that the planner, the plant manager and Dan all accept, so the sign-off discussion is about facts rather than volume.

Three lenses

LensQuestionContoso example
Supply impactCan the plant build and ship what customers ordered, on time?No rotor requisitions: in two weeks ASSY-10 stops for lack of rotors
Inventory value impactAre stock quantities or values, WIP or variances wrong, and by how much?Goods receipt values alternators at $156 in Detroit instead of $150
Control impactIs a control bypassed: approvals, inspections, authorizations?Usage decision possible without the quality role

Rate every plan-to-produce defect through three lenses.

Fix before sign-off if materialWrong valuation or variance with no supply effect, e.g. variance settled to the wrong account
CriticalSupply stops and values are wrong, e.g. goods receipt fails and orders cannot be closed
Low priorityCosmetic or convenience issues, e.g. column order in a planning list
HighSupply at risk, values fine, e.g. no proposals for a critical component
Supply impact against inventory value impact. Control failures are rated High at least, whatever the matrix says.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Quantify the impact

"MRP is wrong" gives the triage meeting nothing to decide on. "MRP creates no purchase requisitions for CMC-RTR-200 in plant 1710; at 2,000 alternators a month, rotor stock of 600 covers only six to seven working days (about 92 a day)" does. For value defects, state the amount per document and per month: a $6 overvaluation on 2,000 alternators a month misstates finished goods by $12,000 a month and creates matching variances.

SeverityDefinition for plan-to-produceExample
CriticalStops planning, production or goods receipt, or misstates inventory materially, with no workaroundOrders cannot be released in plant 1710
HighSupply at risk, control failure, or wrong values with only a costly workaroundNo proposals for a critical component; usage decision without authorization
MediumWrong behavior with a practical workaround and limited valueRework order needs a manual component addition
LowCosmetic or convenience issueOrder print shows the work center description truncated

Contoso's plan-to-produce severity definitions (adapted from the program's defect standard).

Must it be fixed before sign-off?

  1. Is it Critical?Yes → fix and retest before sign-off · No → next question
  2. Is it High?Yes → fix before sign-off, unless the process owner and Dan accept a documented workaround with an owner and end date · No → next question
  3. Does the workaround add daily manual effort in the plant?Yes → plan the fix for hypercare; size the effort · No → schedule in the backlog
  4. Does it affect period-end values?Yes → Dan decides with finance controls · No → plant manager decides
Contoso's decision path for open plan-to-produce defects at sign-off.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Conversion defects deserve a special question: was this broken in ECC too? A defect that reproduces in EP1 is not a conversion regression, but it may still block sign-off if the process owner would not accept it now. Record the answer in the defect, because it changes who fixes it and how quickly.

Reproducing a conversion defect in EP1 changes its label and its owner, but not whether the process owner can accept it.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Triage runs daily during the cycle. Priya chairs it with the production planner, the supervisor, the quality engineer, Dan for value defects and Kenji when custom code is involved. Each defect leaves the meeting with a severity, an owner, a target date and a decision on whether the end-to-end chain can continue on a workaround. Re-rate a defect when new facts appear, for example when a planning defect turns out to affect all materials with a fixed lot size, not just one.

The daily triage turns each new defect into four decisions, with Dan and Kenji pulled in only when value or custom code is involved.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

What would you do?

A defect shows that the end-of-line test operation at TEST-10 can be confirmed with zero yield and no scrap, leaving 12 alternators unaccounted for. No value is wrong yet in the test client. How should it be rated?

DefectSupply lensValue lensSeverity
MRP Live creates no requisitions for CMC-RTR-200Line stops in about a weekNone yetCritical
Variance on order 1000233 settled to the wrong accountNoneP&L classification wrong; Dan must reclassifyHigh
Confirmation with zero yield and no scrap accepted at TEST-10None immediatelyStock and WIP can drift undetectedHigh
Order print shows a truncated operation textNoneNoneLow

Four plan-to-produce defects rated through the supply and value lenses.

Key points
  • Rate defects by supply impact, inventory value impact and control impact.
  • Quantify: days of supply at risk, dollars per document and per month.
  • Critical and High defects block sign-off unless a documented workaround is accepted.
  • Ask whether the defect existed in ECC; it changes ownership, not necessarily severity.

Check your understanding · not graded

Lesson check

  1. 1. MRP creates no proposals for a critical component. Which rating fits best?

  2. 2. Which statement quantifies an inventory value defect usefully?

  3. 3. A control can be bypassed but no value is wrong yet. How is it treated?

  4. 4. Why record whether a defect also exists in ECC?