Lesson 2 of 5

Defining expected results for planning and execution

11 min

Listen to this lesson

0:00 / 8:04

"MRP ran successfully" and "order confirmed" are not expected results. They tell the tester nothing about whether the plan or the postings are right. An expected result is a fact you can calculate before the test from known inputs, then compare with what the system produced. This lesson writes those facts for Contoso's October cycle.

Planning: calculate the proposals first

Inputs for CMC-ALT-100 in plant 1710: planned independent requirements of 2,000 pc for October, stock of 300 pc, safety stock of 200 pc, fixed lot size of 500 pc. One rotor per alternator; rotor stock 600 pc; rotors are bought from Lakeside Components at a standard price of $40. MRP must cover requirements so that projected stock never drops below safety stock.

MaterialCalculationExpected proposals
CMC-ALT-1002,000 required − 300 stock + 200 safety stock = 1,900 net; fixed lot 500Four planned orders of 500 pc (2,000 pc); projected end stock 300 pc
CMC-RTR-200Dependent requirements 2,000 − 600 stock = 1,400 shortagePurchase requisitions for 1,400 pc, dated by planned delivery time
Requisition value1,400 × $40 = $56,000Over the $10,000 threshold, so release is required before a PO

Expected MRP results for the October cycle. Inputs are fictional test data agreed with the planner.

The October expected result for PTP-01 and PTP-02, calculated before the run: four alternator orders and a rotor requisition big enough to need release.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Write the expectations in quantities and dates, not "MRP creates orders". If MRP produces three planned orders, or orders of 1,900, either the master data or the configuration differs from what the planner believes. That is a finding even if nothing "failed". MRP Live in SAP S/4HANA creates purchase requisitions for externally procured material directly, so do not expect planned orders for rotors unless the material is planned with classic MRP; check this against your system's settings.

  1. Inputs fixedRequirements, stock, safety stock, lot size and lead times agreed and frozen in the test client
  2. Expected values calculatedQuantities, dates and proposal types written into the test case before the run
  3. Planning runMRP Live for plant 1710 with the agreed scope
  4. CompareStock/requirements list and material coverage apps against the expected table
  5. Explain every differenceMaster data, configuration or defect; nothing is waved through
Expected results are written before execution and compared after it.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Execution: statuses, movements and stock

Take the first planned order: 500 pc converted to a PP01 production order. For every step, write the status you expect, the goods movement and the stock or value change.

StepExpected statusGoods movement and stockEvidence
Convert planned orderProduction order created (CRTD); planned order goneRotor, stator, housing reservations for 500 eachOrder number, component list, planned costs
ReleaseRELNoneStatus history; availability check result
Goods issueREL, goods movements posted500 of each component leave 171L (movement type 261)Material documents; stock before and after
ConfirmationsPCNF, then CNFNone; activity hours posted to the orderConfirmation numbers; yield and scrap per operation
Goods receiptDLV+500 CMC-ALT-100 (movement type 101), valued at $150 = $75,000Material document, journal entry, stock before and after

Expected execution results for production order 1 (500 pc).

Each status change of production order 1 has an expected goods movement and value, which is what the tester compares, not the status label.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

Costing: the number Dan will check

Contoso's standard cost of $150 per alternator breaks down as rotor $40, stator, housing, regulator and small parts $40, material overhead $8 (10%), assembly labor $26 (0.5 h of ASSYHR at $52), machine time $24 (0.25 h of MACHHR at $96) and production overhead $12 (24%). Planned costs for 500 pc are therefore $75,000. The test plan injects two realistic deviations: five rotors are damaged at ASSY-10 and replaced, and confirmations record 8 extra labor hours and 4 extra machine hours ($416 + $384 = $800). Actual costs become rotors 505 × $40 = $20,200, other components $20,000 and labor and machine $25,800. Costing sheet CMC001 applies overhead as a percentage of actual cost, so the extra rotors and hours carry theirs: material overhead 10% × $40,200 = $4,020 and production overhead 24% × $25,800 = $6,192, together $10,212. Total actual cost is $76,212. Goods receipt credits the order with 500 × $150 = $75,000, so the expected unfavorable variance is $1,212: $220 input quantity variance on rotors ($200 plus $20 material overhead) and $992 on activities ($800 plus $192 production overhead). This is the October test-cycle order (1000233 in lesson 3), not the controlling courses' order 1001200.

Cost elementPlanned (500 pc)ActualExpected variance
Rotor CMC-RTR-200$20,000$20,200$200 input quantity
Stator, housing and other parts$20,000$20,000None
Labor and machine activities$25,000$25,800$800 input quantity
Material overhead (10%)$4,000$4,020$20 on the extra rotors
Production overhead (24%)$6,000$6,192$192 on the extra hours
Credit from goods receipt−$75,000−$75,000Total $1,212 unfavorable
Expected costs and variances for production order 1. Overhead follows costing sheet CMC001, so it rises with the extra rotors and hours.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-303

How the variance reaches the books depends on configuration. With classic period-end processing, which Contoso carried over from ECC, variances are calculated and the order is settled at period end. With event-based production accounting, SAP describes WIP and variances being posted automatically when the order reaches status DLV. Either way, write the expected variance and its category before the test, and name the account it should reach after settlement.

What would you do?

The test case for PTP-01 says: "Expected: MRP creates planned orders for CMC-ALT-100." The run creates one planned order of 2,000 pc. What should Priya do?

Key points
  • Calculate planning proposals from frozen inputs before the run: quantities, dates, proposal types.
  • For execution, expect statuses, movement types, stock and values, with evidence for each.
  • Write the expected variance by category and the account it settles to.
  • Status labels and screenshots are not results; documents and values are.

Check your understanding · not graded

Lesson check

  1. 1. With 2,000 pc required, 300 in stock, 200 safety stock and a fixed lot of 500, how many planned orders are expected?

  2. 2. Why is release expected for the rotor purchase requisitions in the October cycle?

  3. 3. Actual costs are $76,212 and the goods receipt credits $75,000. What is the expected result?

  4. 4. Which evidence best proves the goods receipt step?