Lesson 5 of 5

Testing QM controls end to end

10 min

Listen to this lesson

0:00 / 5:39

QM controls exist to say no: no to an unreleased supplier, no to using stock that has not passed inspection, no to a usage decision without a certificate. A QM test pack that only proves the yes paths proves very little. Priya's team builds the Contoso QM pack around the negative outcomes and the stock type that results from each decision.

Supplier controlsRelease, block, release quantity and date in the quality info record
Receipt controlsLot creation at GR, certificate confirmation, source inspection and skips
Production controlsIn-process lot at release, results at operations, 04 lot at receipt
Stock controlsInspection and blocked stock cannot be consumed or delivered
Follow-upComplaints with tasks, return deliveries, analytics by supplier
The layers of a QM control test, from supplier to follow-up.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-302

Test cases

CaseExpected resultEvidence
PO for a blocked supplierPO refused or warned as configuredMessage text; no PO number created
PO over release quantityPurchasing stopped at the limitInfo record quantities; message
GR for an inspected materialLot 01 created; stock in quality inspectionLot number, material document, stock by type
UD without certificateUD blocked with an errorError message; lot status unchanged
Order release with 03 activeOne in-process lot for the orderLot number linked to the order
GR from production with 04 activeFinished goods in quality inspection stock; delivery not possibleStock by type; failed delivery attempt
Rejecting UDStock to blocked; complaint created with tasksMaterial document 350; notification number and tasks
Return deliveryBlocked stock returned to the supplierMaterial document 122 referencing the PO

A QM control pack for procurement and production.

Evidence: lots and stock types

For every case, the two most important pieces of evidence are the inspection lot (number, origin, status, usage decision and quality score) and the stock type before and after (unrestricted, quality inspection, blocked) for the affected material and plant. Add the material document numbers for each posting, and for negative tests the exact message text. With those, anyone can re-perform the check later.

For each QM test case the evidence is a small data set: the lot, the material documents and stock by type before and after.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-302
  1. BeforeRotor stock in plant 1710 by stock type; open lots for the material
  2. TriggerGR from Lakeside, or release and receipt of the alternator order
  3. LotLot number, origin and status recorded
  4. DecisionUD code, quality score, stock postings
  5. AfterStock by type compared with the expected movement; negative test attempted
The evidence chain for one QM test.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-302

In a system conversion, add a data reconciliation. Count quality info records, materials with active inspection types and open inspection lots in ECC (EP1) and in the converted system, by plant. Open lots at cutover are a particular risk: stock in quality inspection must arrive with its lot, or it can never be released. Luis's cutover plan for Contoso includes a step to bring open lots to a usage decision before the cutover window where possible, and to list the rest.

Open inspection lots are a cutover item: decide what can be decided before the window, and prove the rest arrive with their stock.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-302

What would you do?

Every QM test case passes except one: a usage decision without a certificate goes through without an error. The team is short of time. What should Priya do?

Contoso's QM pack runs in SAP Cloud ALM as test cases linked to the procurement and production solution processes, so a failed control appears as a defect against the process it protects. After go-live the same negative tests form the QM part of the release regression in CMR, because a transport that changes a QM control key or an inspection setup can remove a control silently.

Key points
  • Build QM tests around negative outcomes and the resulting stock type.
  • Evidence: lot number, origin, status, UD and score; stock by type before and after; document numbers.
  • Cover supplier, receipt, production, stock and follow-up controls.
  • In a conversion, reconcile info records, inspection setup and open lots.

Check your understanding · not graded

Lesson check

  1. 1. Which two pieces of evidence matter most for each QM test?

  2. 2. What should a PO for a blocked supplier produce in a passing test?

  3. 3. Why reconcile open inspection lots at cutover?

  4. 4. Why keep the negative QM tests in the release regression after go-live?