Evaluating capacity load

10 min

Listen to this lesson

0:00 / 6:03

Capacity evaluation answers simple questions: which work centers are overloaded, when, by how much, and which orders cause it? SAP S/4HANA offers several tools. In current releases the main one for planners is the Fiori app Manage Work Center Capacity.

Manage Work Center Capacity

According to SAP Learning, the app's overview lists the selected work center capacities with aggregated figures for an evaluation horizon: maximum load, time of the first overload, backlog of overdue orders, total requirements, average load, time of first critical load, overall percentage load and total available capacity. A chart shows utilization per period, colored for normal load, critical load and overload, and the thresholds for those bands can be set individually.

OverviewAll Detroit work centers for the next four weeks: max load, first overload, backlog, average load
Work center detailASSY-10 utilization chart by day or week with normal, critical and overload bands
Pegged requirementsThe individual orders and operations behind each bar
ShiftsThe work center's shifts, which can be changed interactively to add capacity
Drilling down in Manage Work Center Capacity.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-206

From the overview you navigate to a single work center. The detail view shows the chart and the pegged requirements: the operations and orders that make up each period's load. It also shows the work center's shifts, which a planner can change interactively, for example to add an extra shift in a peak week.

Other evaluation tools

ToolWhat it showsNotes
Manage Work Center Capacity (Fiori)Load, overloads, backlog, pegged orders, shiftsSAP's current evaluation app
Work center load reportLoad by work center and period in a listNamed in SAP Learning as an evaluation report
Stock/requirements listCapacity situation for a material's ordersUseful when a planner starts from a material
Classic CM transactions (for example CM01)Standard load overviews in SAP GUISAP Learning states CM* transactions are to be replaced by the Fiori apps

Capacity evaluation tools.

HealthyLoad below 100% and no backlog: no action
Under-plannedSpare capacity but overdue work exists: release or expedite overdue orders
PeakOverloaded but current: level by moving operations or adding a shift
FirefightingOverloaded and behind: re-plan with sales and production; consider overtime
Reading an evaluation: load against backlog.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-206

A practical weekly routine for the Detroit planner: open the overview for the plant’s critical work centers and the next four to six weeks; sort by time of first overload; drill into the earliest one; read the pegged orders; then decide between moving work, adding capacity or escalating. Record the decision in the order or the meeting notes so that the next evaluation can be compared with it.

Colors in the capacity app are only as meaningful as the thresholds behind them, so Detroit agrees one set and writes it into the tests.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-206

Evaluation is also where data quality shows up. A work center with no available capacity maintained will look permanently overloaded; a routing with standard values in the wrong unit will create absurd loads; an operation with a control key that should not be capacity-relevant will add phantom load. Treat strange numbers as master data findings first.

A load that makes no sense is usually a master data symptom; each pattern points at a different record.
The Sign-Off Table · thesignofftable.com/academy/sap-pp-206

What would you do?

Grace wants one number per plant for the weekly steering meeting. The planner suggests "average load across all Detroit work centers". What is the problem with that?

Walkthrough: the Monday capacity review

  1. Open Manage Work Center Capacity with the variant "Detroit critical" (WIND-10, ASSY-10, TEST-10; horizon four weeks; daily buckets).
  2. Sort by time of first overload. ASSY-10 is overloaded on Monday of week 2 at 122%.
  3. Open ASSY-10 and read the pegged requirements: two production orders for CMC-ALT-100 and one planned order from MRP controller 101.
  4. Check the backlog figure: one order from last week is overdue because it was built but never finally confirmed. Ask the supervisor to confirm it; the phantom load disappears.
  5. For the real overload, decide: level (lesson 3), add a shift in the app, or escalate. Record the decision in the planning meeting notes.

Classic SAP GUI reports such as CM01 (load overview), CM07 (variable overview) and the capacity evaluations still exist in SAP S/4HANA Private Edition, which helps planners during the transition. SAP positions the Fiori apps as the target, and SAP S/4HANA Cloud Public Edition offers only the apps.

Key points
  • Manage Work Center Capacity shows load, first overload, backlog and pegged orders per work center.
  • The detail view shows the operations behind each period and the work center's shifts.
  • Critical and overload thresholds can be set individually; agree them per plant.
  • Strange loads usually point to master data: capacity headers, standard values, control keys.

Check your understanding · not graded

Lesson check

  1. 1. What are pegged requirements in Manage Work Center Capacity?

  2. 2. Which figure tells you when the first overload occurs?

  3. 3. Why agree critical-load thresholds per plant?

  4. 4. In the Monday review, an overdue order turns out to be built but never finally confirmed. What should the planner do?