Course quiz

Capacity Planning Basics

Keep this: job aid

Capacity planning card

  • Load = requirements ÷ available capacity; above 100% is overload.
  • Available: calendar, shifts, breaks, utilization, individual capacities (capacity header).
  • Requirements: setup + quantity × time per piece from operation standard values.
  • Evaluate in Manage Work Center Capacity: max load, first overload, backlog, pegged orders.
  • Level with Capacity Scheduling Table (list) or Capacity Scheduling Board (graphical).
  • Strategy = planning mode + scheduling control + direction.
  • Dispatched planned orders are firmed; dispatched operations show DSPT.
  • Classic graphical planning table (CM21) is compatibility scope: on-premise use ended May 31, 2026; cloud subscriptions (RISE) run longer (check Note 2269324 for the current date). Plan the move to Fiori apps.
  • PP/DS: license SAP S/4HANA Manufacturing for planning and scheduling; confirm license, scope, master data and skills with an SME first.
  • Test with hand-calculated loads and relative dates; record the system date.