Lesson 3 of 5

Rehearsals

11 min

A cutover you have not rehearsed is a cutover you are doing for the first time in production. Rehearsals, usually called mock cutovers, run the runbook end to end in a production-like environment, with production-like data volumes, the real team and the real clock. The final rehearsal, the dress rehearsal, proves that the final runbook works as written, in the time available, with the people who will do it on the night.

What each rehearsal is for

Mock 1Mock 2Dress rehearsal
PurposeFind sequence, mapping and tooling gapsProve full volumes, timings and fallbackProve the final plan exactly as it will run
DataFull or large sampleFull production-like volumesFull volumes, fresh copy
PeopleCore teamReal owners, including business validatorsExactly the go-live team and roster
OverrunsExpected and measuredShould be small and explainedNot acceptable; must finish without heroics
ExitEvery task attempted; issues loggedFits the window; fallback timedFits the window with agreed contingency; no open go-live critical issues
Each rehearsal has a different job. Contoso planned two mocks and a dress rehearsal.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-301

Contoso's rehearsals

Mock 1 took 71 hours against Contoso's 60-hour window. That was the useful result: it showed where the time went, most of it in waits between tasks and in a load that had to wait for a manual step. Mock 2, with a corrected runbook and full volumes, fitted the window with only 1.5 hours of float, and it also measured the fallback: restoring the pre-cutover backup and reopening the legacy system took nine hours. After Luis moved static checks into pre-cutover and parallelized stock reconciliation, the dress rehearsal finished with four hours of contingency.

  1. Late RealizeMock 171 hours against a 60-hour window; waits and sequence gaps found
  2. Early DeployMock 2Fits with 1.5 hours of float; fallback measured at nine hours
  3. BetweenRunbook changesStatic checks moved out of window; stock reconciliation split by plant
  4. Deploy, about three weeks before go-liveDress rehearsalFinishes with four hours of contingency; runbook frozen
Contoso's rehearsal sequence and what each run proved.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-301

Making a rehearsal realistic

  • Environment. Use a production-sized copy, ideally built the way production will be, so load and conversion timings mean something.
  • Data. Use a recent copy of production data, protected according to your data privacy rules, with full volumes by Mock 2.
  • People. The people who will do the job on the night, including business validators and approvers, not stand-ins. A stand-in hides how long the real approver takes.
  • Clock. Run in shifts across a weekend if that is how the real cutover runs. A rehearsal spread over two weeks of office hours proves nothing about timing.
  • Late changes. Include every fix and transport planned for go-live. A dress rehearsal that excludes late changes does not prove the real plan.

Measure everything

Assign a timekeeper whose only job is to record actual start and end times, and any waits, for every task. After each rehearsal, compare actuals with plan, recalculate the critical path and the remaining float, and write a lessons log. Every lesson should lead to a runbook change or a recorded decision not to change.

  1. RunExecute the runbook against the clock
  2. RecordTimekeeper logs actual times and waits
  3. AnalyzeCritical path, float, failed and late tasks
  4. ChangeRunbook, work instructions, roster, data fixes
  5. Re-proveNext rehearsal shows whether the change worked
The rehearsal improvement loop. Changes not re-proved in a later rehearsal are still assumptions.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-301

Test the fallback too

Rehearsals should prove not only the way forward but also the way back. Mock 2 is a good place to execute the fallback: restore the target to the pre-cutover backup, reopen the legacy system, re-enable interfaces and confirm that business can resume. Measuring how long that takes gives you the latest safe time to decide on fallback, which Lesson 5 uses.

What would you do?

The team proposes to skip the dress rehearsal because Mock 2 went well and the developers want more time for performance fixes. What should Grace decide?

Key points
  • Mock cutovers run the runbook end to end with production-like data, real people and the real clock.
  • Mock 1 finds gaps, Mock 2 proves volumes and fallback, the dress rehearsal proves the final plan.
  • A timekeeper records actuals; every lesson becomes a runbook change or a recorded decision.
  • Test the fallback in a rehearsal and measure how long it takes.

Check your understanding · not graded

Lesson check

  1. 1. What is the purpose of the dress rehearsal?

  2. 2. Why should rehearsals use the real business approvers rather than stand-ins?

  3. 3. What should happen to each lesson from a rehearsal?

  4. 4. Why test the fallback during a mock?