The Sign-Off Table

Lesson 5 of 5

Preparing and getting P2P sign-off

12 min

Sign-off is a decision, not a ceremony. The procurement process owner and Dan, for the finance steps, are being asked: based on the evidence, are you willing to run your business on this process? The sign-off package exists so they can answer that question in an hour, not by redoing the testing.

What goes in the package

SectionContentContoso example
Scope and coverageCoverage map against scope items and variants; what is out of scope and whyJ45, 18J, 22Z, BMK, J60 covered; consignment out of scope (not used)
Results summaryTests planned, run, passed, failed, blocked, by scope item and risk64 planned, 64 run, 61 passed, 3 failed and retested
Evidence indexWhere the evidence for each test livesTest management records with document chains
Open defectsEvery open defect with severity, workaround, owner, fix date2 medium, 3 low; no critical or high
Accepted risksRisks the owner accepts, with mitigation, owner and expiryService approval notification workaround until release 2
ReconciliationsGR/IR per PO item, supplier balances to G/L, stock value to G/L at cycle endAll zero differences or explained
Roles and controlsApproval, tolerance, duplicate check and segregation of duties testsAll passed, including negative tests
DependenciesWhat sign-off assumes from other streamsSupplier business partners and open POs reconciled after mock conversion 2

Contents of Contoso's P2P sign-off package.

  1. Week -3Exit criteria checkPriya checks coverage, pass rates, defect status against agreed exit criteria
  2. Week -3Package assembledResults, evidence index, defects, risks, reconciliations
  3. Week -2Review meetingProcess owner, Dan, Priya, Grace walk through the package; questions answered with evidence
  4. Week -2DecisionSign, sign with conditions, or refuse with reasons
  5. Week -1Go/no-go inputSigned P2P sign-off feeds Luis's cutover go/no-go
From exit criteria to signature.
The Sign-Off Table · thesignofftable.com/academy/sap-mm-303

Exit criteria

Agree exit criteria at the start of the test phase, not the week before sign-off. Contoso's P2P exit criteria: all planned tests executed; all high-risk tests passed; no open critical or high defects; every control test passed including negative tests; GR/IR, supplier and stock reconciliations clean or explained; open medium and low defects have workarounds and owners. If the criteria are met, sign-off is a confirmation. If not, the package says exactly which criterion is missed.

SignatureProcurement process owner; Dan for invoice and payment steps
Accepted risksEach with mitigation, owner and expiry date
Open defectsRated, with workarounds and fix dates
Results and reconciliationsPass rates by scope item and risk; GR/IR, supplier and stock reconciliations
CoverageScope items, variants, exceptions and controls traced to tests
A sign-off rests on coverage, results, defects and risks, in that order.
The Sign-Off Table · thesignofftable.com/academy/sap-mm-303

Recording accepted risks

An accepted risk is a known gap the business chooses to live with for a while. Write it so that someone reading it in six months understands it: what can go wrong, how likely and how costly, what compensating step is in place, who owns it, and when it expires. "Accepted: notification issue" is not a risk record. "Service entry sheet approval notifications go to the purchasing group instead of the cost center manager; purchasing forwards them manually within one day; owner: procurement process owner; expires with the fix in release 2, planned for November" is.

What would you do?

The day before the review, a high-severity defect is still open: payment advices to suppliers show the wrong invoice reference. A manual workaround exists (AP emails corrected advices). The process owner wants to sign anyway. What should happen?

Running the review meeting

Send the package two days before the meeting so the signatories can read it. In the meeting, Priya presents coverage first, then results, then open defects and risks, and the reconciliations last, because they are the summary proof that the process works financially. Questions are answered by opening the evidence, not from memory. The meeting ends with one of three outcomes recorded in the minutes: signed, signed with named conditions, or not signed with the missing criteria listed and a date for the next review.

Keep the signed package with the test evidence. Auditors, the next release's test team and the hypercare team will all use it. And plan to revisit accepted risks at their expiry dates: a risk accepted "until release 2" that nobody follows up becomes a permanent gap.

Key points
  • The sign-off package lets the owner decide on evidence: coverage, results, defects, risks, reconciliations, controls, dependencies.
  • Agree exit criteria early; sign-off then confirms them or names what is missing.
  • Record accepted risks with impact, mitigation, owner and expiry.
  • Use conditional sign-off for known, time-bound gaps; never hide or downgrade defects.

Check your understanding · not graded

Lesson check

  1. 1. Who should sign off the procure-to-pay process?

  2. 2. When should exit criteria be agreed?

  3. 3. Which is a complete accepted risk record?

  4. 4. Which reconciliation belongs in the P2P sign-off package?