Testing and Signing Off Procure-to-Pay
Course quiz
Testing and Signing Off Procure-to-Pay
Keep this: job aid
P2P test and sign-off card
- Baseline: J45 direct materials, 18J requisitioning, 22Z services, BMK returns, J60 payables (check your edition in Process Navigator).
- Add layers: company variants, exceptions and negatives, integration points.
- Expected results before execution: statuses, quantities, values, postings, evidence.
- Variance tests expect: posted, blocked for payment, excluded from payment run, released, paid.
- Run end to end with production roles; keep the document chain and journal entries.
- Outputs to a test mailbox; payment files to a test channel. Always.
- Rate defects by spend, supplier impact and control risk; control failures are at least high.
- Package: coverage, results, evidence index, defects, accepted risks, reconciliations, controls, dependencies.
- Accepted risk = impact + mitigation + owner + expiry.