Master data is easy to look at and hard to prove. A supplier record can look perfect on screen and still produce a PO with the wrong payment terms, because a partner function points somewhere else or a plant-specific info record overrides the general one. The reliable test is to let the system use the data: create a probe purchase order and check what it proposes.

What a probe PO is

A probe PO is a test PO created with as little input as possible, so the master data has to fill everything else. You enter the product, quantity and plant (and, depending on the test, the supplier), accept every proposal and compare the result with an expected-values sheet. In a test client like 100, you can then post a receipt and an invoice to prove accounts. In production, master data teams sometimes create probe POs and then delete them without sending output; agree this with the process owner first.

  1. Expected valuesWrite down what each field should be before you start
  2. Minimal inputProduct, quantity, plant; leave supplier empty to test source determination
  3. Capture proposalsSupplier, price, payment terms, incoterms, delivery date, purchasing group, GR-based IV
  4. Post follow-ons (test client)Goods receipt and invoice to see accounts and matching behavior
  5. Compare and recordPass or defect for each field, with document numbers as evidence
The probe PO test procedure.
The Sign-Off Table · thesignofftable.com/academy/sap-mm-201

The expected-values sheet

CheckWhere it comes fromExpected for CMC-RTR-200 / plant 1710
Supplier proposedSource list fixed entry or regular supplierLakeside Components
Net priceInfo record or contract condition$42.00 per unit
Payment termsSupplier purchasing org dataNet 30
IncotermsSupplier purchasing org data or info recordFCA
Delivery datePlanned delivery time (plus GR processing time for planning)PO date + 10 days
Purchasing groupProduct purchasing view or info record001
GR-based invoice verificationSupplier purchasing org dataSet
Inventory account at goods receiptValuation class in accounting viewRaw materials inventory
Price difference at goods receiptPrice control S, standard $40.00$2.00 per unit to price differences

Contoso's expected-values sheet for the rotor probe PO.

Negative probes

Positive probes prove the right data is used. Negative probes prove controls work. Try a blocked source: the PO should be refused. Try a product without a valid source list entry where one is required: the PO should be refused. Try a supplier blocked for purchasing: the PO should be refused. Each negative probe is a short test, and each one proves a control the auditors will ask about.

Positive, singleNew supplier: one PO proves its purchasing data defaults
Negative, singleBlocked supplier: PO creation is refused
Positive, combinationSupplier + product + plant: price, dates, accounts all right
Negative, combinationBlocked source list entry for the product in this plant: PO refused
Four kinds of probe to cover data and controls.
The Sign-Off Table · thesignofftable.com/academy/sap-mm-201

Probes are not only for go-live. Keep a small set as a regression pack and rerun it after changes that touch master data: a new purchasing organization, a change to account determination, a mass price update or a release upgrade. Because the expected values are written down, a rerun takes minutes and shows at once whether anything moved.

What would you do?

A probe PO for rotors in plant 1720 proposes $44.00, but the expected value is $42.00 and the purchasing org info record shows $42.00. What do you check next?

Key points
  • Probe POs prove master data by letting the system fill a PO from minimal input.
  • Write expected values before testing; compare field by field.
  • Negative probes prove controls such as blocked sources and required source lists.
  • Post receipt and invoice in a test client to prove account determination.

Check your understanding · not graded

Lesson check

  1. 1. What is a probe purchase order?

  2. 2. Why write expected values before creating the probe PO?

  3. 3. Which is a negative probe?

  4. 4. How do you prove the valuation class is right?