Lesson 3 of 6

Spare parts and external services

9 min

Listen to this lesson

0:00 / 6:42

Most repairs need parts, and some need outside help. SAP handles both through the order's components and operations, and both reach far outside maintenance: stock parts touch inventory, and non-stock parts and services touch purchasing, receiving and accounts payable.

Stock parts: reservation and goods issue

The bearing and the drive belt are stock items in storage location 171S, Detroit's spare parts store. When Rosa adds them to operation 0010, SAP creates a reservation. SAP's training notes that the reservation is created when the material is assigned, and that at release, at the latest, it becomes relevant: the storeroom can then pick and issue the parts. The goods issue to the order (movement type 261 in standard settings) reduces stock and posts the parts' value to the order as actual cost. The sequence is: assign component, reserve, release the order, print the pick list, issue.

A stock part on order 4001250: the reservation exists from planning, becomes relevant at release, and the goods issue posts the part's value to the order.
The Sign-Off Table · thesignofftable.com/academy/sap-eam-202

Non-stock parts: the purchase requisition link

The tension sensor is a non-stock item. Adding it to the operation makes SAP create a purchase requisition, account-assigned to the order. Purchasing turns it into a purchase order; when the sensor arrives, the goods receipt posts its cost directly to the order rather than into stock; the invoice follows. The delivery address can be set on the order so the part goes to the Detroit maintenance shop, not the main receiving dock. Contoso's approval thresholds apply to these documents like any other: requisitions over $10,000 need release, purchase orders over $25,000 need approval.

StepStock part (bearing)Non-stock part (tension sensor)
Planned on the orderReservationPurchase requisition
ProcuredAlready in 171SPurchase order to the supplier
Arrives at the orderGoods issue from stockGoods receipt straight to the order
Cost on the orderAt the time of issueAt goods receipt, adjusted by the invoice
EvidenceMaterial document with the order as account assignmentRequisition, PO and receipt linked to the order
Stock and non-stock spare parts side by side.
The Sign-Off Table · thesignofftable.com/academy/sap-eam-202

External services

Some work is done by contractors. An operation with an external control key creates a requisition for the work itself. SAP describes two modes: compatibility mode, with external processing (PM02, receipt by goods receipt) and external services (PM03, receipt by service entry), and an enhanced procurement mode for lean services, available in the web apps. Contoso uses Riverbend Facility Services for vibration analysis on line 1, planned as an external operation; Riverbend's work is confirmed through a service entry and invoiced against the PO. The program must decide which mode each order type uses before testing starts, because the evidence differs.

External work runs through one of two procurement modes; the control key on the operation picks the path in compatibility mode.
The Sign-Off Table · thesignofftable.com/academy/sap-eam-202
  1. External operationOperation 0030 vibration analysis, control key for external service
  2. RequisitionCreated from the order; routed to purchasing
  3. Purchase orderTo Riverbend Facility Services; approved if over $25,000
  4. Service entryWork performed is recorded and approved
  5. InvoiceMatched to the PO and service entry; cost on the order
An external service from operation to invoice.
The Sign-Off Table · thesignofftable.com/academy/sap-eam-202

In testing, the storeroom's view matters as much as the planner's. Contoso's storeroom key user checks that maintenance reservations appear in the pick list for storage location 171S with the order number, the requirement date and the recipient. She also checks what happens when a technician needs one more bearing than planned: an unplanned issue to the order is allowed, but it should be the exception, and SAP's analytics distinguish planned withdrawals (with a reservation) from unplanned ones.

The postings behind spare parts

EventMovement or documentAccount assignmentWhat to check
Stock part issued to the orderGoods issue, movement type 261Order 4001250Material document lists the order; stock in 171S reduced
Issue reversed (wrong part)Movement type 262Order 4001250Order cost reduced by the same value
Unused part returned to the storeReturn to stock against the order (262)Order 4001250Reservation and stock updated
Non-stock sensor receivedGoods receipt 101 against the POAccount assignment category F (order)Cost lands on the order, not in stock
Riverbend service acceptedService entry sheet against the POOrder operation 0030Acceptance recorded before invoice

Spare parts and service postings, and the evidence each leaves (standard movement types; check your configuration).

Key points
  • Stock components create reservations; at release, at the latest, they can be issued to the order.
  • Non-stock components create purchase requisitions account-assigned to the order; the receipt posts cost to the order.
  • External work runs through requisition, PO, goods receipt or service entry, and invoice.
  • Approval thresholds and availability checks apply to maintenance purchases too.

Check your understanding · not graded

Lesson check

  1. 1. A non-stock spare part on a maintenance order typically creates what?

  2. 2. When does a stock reservation on a maintenance order become relevant for withdrawal at the latest?

  3. 3. Where does the cost of a non-stock part go when it is received?

  4. 4. Riverbend's vibration analysis is an external service operation. How is the work received?