Lesson 4 of 5

Writing the migration runbook

9 min

A migration runbook is the step-by-step script for executing the migration: every action, in order, with its owner, timing, predecessor and evidence. It is written during the mocks, improved after each one, and on go-live weekend it is the only plan anyone follows. If a step is not in the runbook, it does not happen; if it happens anyway, it should be added.

Cutover planThe whole go-live: technical, business, data, communication; owned by Luis
Migration runbookAll data migration steps in sequence, with owners and checkpoints
Object work instructionsHow exactly to extract, transform, load and validate one object
EvidenceLogs, counts, reconciliation reports and sign-offs produced by each step
Where the migration runbook sits. It is a chapter of the cutover plan and points down to detailed work instructions.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-304

What every step contains

FieldPurposeExample
Step IDUnique reference for status and issuesMIG-210
ActionOne clear action, starting with a verbLoad business partner delta (customers) via Migrate Your Data
PredecessorsSteps that must be complete firstMIG-200 delta extract validated
Owner and backupNamed person on shift, plus a named backupMigration specialist A; backup B
System and clientWhere the step runsProduction system CMP, production client (never test client 100 in CMQ)
Planned start and durationFrom the last timed rehearsalSat 02:00, 1.5 h
Actual start and endFilled during executionRecorded live
EvidenceWhat proves completionMessage log export; record count matches extract
CheckpointWhether a go/no-go decision followsCheckpoint 2 after MIG-260
ContingencyWhat to do if it failsRerun after fix within 1 h; else escalate to Luis

The fields of a runbook step. Contoso kept its Wave 2 runbook as a shared, versioned workbook.

Writing good steps

  • One action per step, so status is unambiguous.
  • Durations from measured rehearsals, not estimates.
  • Every step that changes data has a validation step after it, owned by someone else where possible.
  • Decision points are steps too: "Checkpoint 2: Dan confirms AR reconciliation; Luis decides go or stop."
  • Handovers between shifts are explicit steps with a briefing and a status snapshot.
  • Contingency is written next to the step, not in a separate document nobody opens at 3 a.m.

The runbook improves with every mock

  1. Draft before Mock 1Steps from the load sequence and work instructions
  2. Execute and recordActual times, deviations and unplanned steps captured live
  3. Review after the mockMissing steps added, durations updated, owners and contingency fixed
  4. Version and approveNew version issued with a change log; Luis approves
  5. Freeze before dress rehearsalOnly the go-live version runs in the dress rehearsal and on the day
The runbook lifecycle. Each mock turns surprises into written steps.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-304

A useful measure of runbook maturity is the number of unplanned steps per rehearsal: things people had to do that were not written down. Contoso counted 41 in Mock 1, 12 in Mock 2, 3 in Mock 3 and none in the dress rehearsal. That trend gave Grace more confidence than any status color.

What would you do?

During Mock 3, a migration specialist realizes that the pricing condition load needs a manual step (releasing a condition table) that is not in the runbook. He does it and carries on. What should happen next?

Key points
  • The migration runbook is the step-by-step script of the migration, a chapter of the cutover plan.
  • Each step: ID, action, predecessors, owner and backup, system and client, timing, evidence, checkpoint, contingency.
  • Durations come from rehearsals; decision points and handovers are steps too.
  • Update and version the runbook after every mock; track unplanned steps toward zero.

Check your understanding · not graded

Lesson check

  1. 1. What is a migration runbook?

  2. 2. Where should planned durations come from?

  3. 3. What does a falling count of unplanned steps show?

  4. 4. Why must every step name the system and client?