Lesson 3 of 5

Delta and freeze

9 min

Two problems collide on go-live weekend. The old system keeps changing until the moment it is switched off, and the new system cannot absorb everything in one short window. The answer is a combination of freezes, which stop or limit change, and deltas, which carry across what changed after an earlier load.

Kinds of freeze

FreezeWhat stopsTypical timingContoso example
Design and rule freezeChanges to mapping and transformation rulesBefore the final rehearsals (Mock 3)Payment terms mapping locked after Mock 2
Configuration and transport freezeNon-critical transports to the target landscapeWeeks before go-liveOnly cutover-critical fixes may be imported to production
Master data freezeCreation and change of master data in the source, or changes tracked for deltaDays to weeks before cutoverNew customers only by exception, logged for re-entry
Transactional freeze (business blackout)Posting in the source systemStart of the cutover windowLast legacy ERP shipments Friday 6 p.m.; legacy ERP locked for postings

The main freezes. Each needs a date, an owner and an exception process.

Pre-load plus delta

Master data changes slowly and there is a lot of it. Loading it during the cutover window wastes precious hours. Many programs therefore pre-load master data into production before the window, often a week or two before go-live, and then load only the delta: records created or changed since the pre-load extract. Open items and balances, which change every day and must be exact at the cutover date, are loaded during the window after the transactional freeze.

Load at cutoverSmall and changing: open orders, open items, balances
Load at cutover, optimizedLarge and changing: inventory balances, high-volume open items; parallel jobs and rehearsed timing
Pre-load or enter manuallySmall and stable: banks, a few reference records
Pre-load plus deltaLarge and stable: business partners, products, bills of material
Where each object belongs in the cutover plan, by volume and rate of change.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-304

How deltas are handled

There is no single delta mechanism; the right one depends on the object and the tool. The common options are:

  • Reload changed records: extract records created or changed since the pre-load (using change dates or change logs in the source) and load them as new or changes. Needs a tool path that can update as well as create.
  • Dual maintenance: during the master data freeze, any essential change is made by hand in both systems and logged. Practical only for small numbers.
  • Freeze and log: changes are forbidden except by exception; each exception is logged and re-entered in the new system after go-live.

Whichever option you choose, rehearse it. A delta that has never been tested in a mock is the most common gap in migration plans, because the mocks usually load everything from scratch and the delta path is only exercised on the real weekend. Plan at least one rehearsal, ideally Mock 3 or the dress rehearsal, that runs exactly as go-live will: pre-load, a period of change, then delta plus open items.

  1. T-14 daysMaster data extractBusiness partners, products and dependent master data extracted from the legacy ERP
  2. T-12 daysPre-loadLoaded into production SAP S/4HANA (CMP) for company code 1910 and validated by owners
  3. T-12 to T-1Master data freezeChanges by exception only, each logged for the delta
  4. T-0 Friday 6 p.m.Transactional freezeLast postings in the legacy ERP; system locked
  5. T-0 to T+2Delta and open itemsMaster data delta, then open orders, stock, open items and balances; reconciliation and sign-off
A pre-load plus delta pattern for the go-live of company code 1910, as rehearsed in the dress rehearsal.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-304

What would you do?

During the Alternadores del Norte master data freeze, its sales operations need to set up a new fleet customer urgently to accept a large order. What should happen?

Key points
  • Freezes limit change: rules, transports, master data and finally postings.
  • Pre-load large, stable master data before the window; load only deltas at cutover.
  • Load open items and balances after the transactional freeze so they are exact at the cutover date.
  • Every freeze needs an exception process; every delta path must be rehearsed.

Check your understanding · not graded

Lesson check

  1. 1. Why pre-load master data before the cutover window?

  2. 2. Which data is normally loaded after the transactional freeze?

  3. 3. What is a common gap in migration plans regarding deltas?

  4. 4. What should every freeze have besides a date?