Week 10 of 12

Cutover and the go/no-go call

This is the week the newsletter is named for. Somebody has to sign the go-live. The best go/no-go meetings are short, because the evidence was collected in advance and every item has an owner and a status.

The worst ones are long, because nobody agreed what "ready" means until the room was full.

This week: build the runbook and the readiness checklist

  1. Build the hour-by-hour cutover runbook: predecessor, owner, backup, planned and actual times, validation, and a clearly marked point of no return.
  2. List the go/no-go criteria with a threshold and evidence for each: SIT and UAT exit, reconciled balances from the final rehearsal, interfaces, roles, performance, support readiness.
  3. Mark which criteria are blocking. A red blocking item means no-go unless someone with authority waives it in writing.
  4. Circulate the checklist 48 hours before the meeting so owners can update their items.

Number of the week

48 hours

is how far ahead the go/no-go checklist should go out, so the meeting reviews evidence instead of collecting it.

Source: The Sign-Off Table go/no-go checklist

Use this week

Next week: hypercare, and why it should end on evidence, not on a date.