The Sign-Off Table
The Infor CloudSuite Testing Playbook

Week 6 of 8

SIT, UAT and roles

Infor’s guide describes the Test phase simply: all workstreams synchronize for end-to-end SIT against agreed entry and exit criteria, then UAT confirms the business accepts the solution. The hard part is making both produce evidence a sponsor can sign.

Security has two layers. Infor OS roles decide who reaches the portal and applications; application security, such as M3 roles or CloudSuite Industrial groups and IDO permissions, decides what they can do. Test both. And plan for sign-off delays: in Panorama’s 2026 report, almost a quarter of projects ran over schedule, most often for organizational reasons.

This week: make SIT end-to-end and UAT signable

  1. Write SIT scenarios as chains, e.g. EDI order → credit check → MRP → manufacturing order → operation reporting → receipt → shipment → invoice → payment.
  2. Every expected result must be checkable: an order number, a status, a posted amount, a OneView reference. Never "screen appears".
  3. Run UAT with production roles, one test user per tester, and include negative tests: what each role must not be able to do.
  4. Agree the UAT sign-off route now: process owner, functional lead, test manager, program director.

Number of the week

Almost 1 in 4

ERP projects ran over schedule; organizational issues such as delayed sign-offs were the most common cause.

Source: Panorama Consulting, The 2026 ERP Report

Use this week

Next week: cutover, go/no-go and hypercare. What the room needs to see.