Lesson 5 of 5

Verification and reporting

12 min

A storyline is not passed when the last step saves. It is passed when the results across all processes are what they should be: quantities, statuses and, above all, the money. This lesson shows how to verify a storyline end to end and how to report integration results so that process owners can sign off.

Verify the chain

Start with the documents. Every storyline should end with a complete chain: sales order to delivery to goods issue to billing to cleared receivable; requisition to PO to goods receipt to invoice to cleared payable; planned order to production order to confirmations to goods receipt to settlement. Use document flow, the purchase order history and the production order's own document views to confirm every link exists and is complete.

Verify the numbers

Then check the values against expectations computed before the cycle. For IT-01, with 200 alternators sold from plant 1710:

CheckWhere to lookExpected for IT-01
Stock movementStock overview for CMC-ALT-100 in 1710 / 171A (for example MMBE)Starting stock plus 200 produced minus 200 issued
Production receipt valueJournal entry for the production goods receipt200 × $150 = 30,000.00 USD debited to finished goods inventory
Cost of goods soldJournal entry for goods issue30,000.00 USD debited to cost of goods sold
Revenue and receivableJournal entry for billingRevenue at the fleet price on the alternator profit center; receivable cleared after payment
GR/IR for rotorsPO history and GR/IR clearingReceived and invoiced quantities match; GR/IR nets to zero for the PO item
Production variancesProduction order after settlementVariance settled per the settlement rule; order balance zero
Cross-process checks for storyline IT-01.
The Sign-Off Table · thesignofftable.com/academy/sap-xpr-302
Documents completeEvery link in every chain exists and has a completed status
Quantities consistentWhat was received, produced, issued and billed agrees across processes
Values correctEach journal entry matches the precomputed expected value
Results add upMargin for the storyline on the profit center equals revenue minus cost of goods sold, with variances explained
Four levels of verification for an integration storyline.
The Sign-Off Table · thesignofftable.com/academy/sap-xpr-302

Reporting outcomes

Integration status reports often drown in counts: 412 test steps executed, 389 passed. Those numbers say little. Report by storyline and by handoff, because that is what the business understands and what sign-off depends on.

StorylineStatusOpen defects (severity)Failed handoffOwner decision needed
IT-01 Fleet order beyond stock, DetroitPassed; reconciliation completeNoneNoneNo
IT-02 Partial rotor supplyPassed with workaround in cycle 1; rerun needed1 (high)Plan to produce → productionYes: accept fix date
IT-03 ChicagoFailed2 (high, medium)Billing → finance: wrong profit centerYes: master data correction plan
IT-04 Credit blockPassedNoneNoneNo
An integration status report by storyline.
The Sign-Off Table · thesignofftable.com/academy/sap-xpr-302

Defects at the handoffs

Tag every integration defect with the handoff where it appeared and the area where it was caused. After a cycle, the pattern is often striking: at Contoso, most cycle 1 defects sat at two joins, master data to billing and production to finance. That tells the program where to strengthen string tests and data reviews before the next cycle, and it tells the process owners which joins deserve the closest look at sign-off.

Exit criteria

  • All main storylines executed end to end without workarounds.
  • No open critical or high defects on main storylines, or each accepted by the process owner with a dated plan.
  • Financial reconciliation complete for each main storyline.
  • Every failed handoff from earlier cycles retested and passed.
  • Evidence filed: handoff notes, document numbers, reconciliations, defect records.

What would you do?

At integration exit, 96 percent of steps passed. IT-03 (Chicago) failed because revenue posted to a default profit center. The sales lead argues it is "only one storyline and a master data fix". What should the process owners decide?

Key points
  • Verify the chain: every document link exists and is complete.
  • Verify the numbers against precomputed values: stock, inventory, COGS, revenue, GR/IR, variances.
  • Finance reconciles each main storyline before exit.
  • Report by storyline and handoff, not by step counts.
  • Exit criteria cover workarounds, open defects, reconciliation, retests and evidence.

Check your understanding · not graded

Lesson check

  1. 1. When is a storyline passed?

  2. 2. What is the expected production receipt value for 200 alternators in plant 1710?

  3. 3. Why report integration status by storyline and handoff?

  4. 4. A storyline passed only with a workaround. What does exit require?