Lesson 4 of 6

Criteria, metrics and reporting

13 min

Listen to this lesson

0:00 / 10:15

Entry and exit criteria are where a strategy earns its keep. They turn "are we ready?" from an opinion into a check. Metrics are the evidence that the criteria are met, and reporting is how that evidence reaches the people who decide.

Entry and exit criteria

Each level needs entry criteria (what must be true to start) and exit criteria (what must be true to finish). Write them so they can be checked from data. "Environment ready" is not checkable; "transport baseline for wave 3 imported to QAS client 100 and smoke test passed" is.

LevelEntry criteria (examples)Exit criteria (examples)
SITUnit and string tests passed for in-scope processes; test cases Prepared and linked in Cloud ALM; data load cycle 2 reconciled; interfaces connected; testers have roles100% of planned test cases executed; 95% passed; no open S1; S2 only with approved workaround; all closed defects retested
UATSIT exit met or exceptions accepted; key users trained; UAT test cases reviewed by process ownersAll UAT test cases executed; process owners accept results; open defects listed with owners and dates
Data migrationMapping signed off; load programs unit-testedReconciliation within agreed tolerance; business data owners sign
Regression (Run)Upgrade or change applied in test system; regression plan PreparedRegression pack executed; no new S1 or S2; differences explained

Example criteria for Contoso. Thresholds are program decisions, not universal rules.

Not readyMany failures and some in critical processes; fix and retest before any gate
Not ready despite the number95% passed but fleet order to cash fails; a named critical process must pass completely
Investigate, then decideMany cosmetic failures; check capacity and retest plans before exit
Recommend exitHigh pass rate, only low-severity failures with owners and dates
Why a pass-rate threshold needs a severity rule beside it: a high number can still mean not ready.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-301

Criteria and quality gates

Link each level's exit criteria to the SAP Activate quality gate that relies on it. SIT and UAT exit feed the end-of-Realize gate; cutover rehearsal checks and OAT feed the go-live decision in Deploy. In SAP Cloud ALM, put the criteria into the quality gate checklists so each gate asks the same questions and stores the answers.

  1. SIT exitCriteria checked from Cloud ALM data
  2. UAT exitProcess owners accept their processes
  3. End-of-Realize gateUses SIT and UAT exit results
  4. Rehearsal checks and OATCutover runs on time; solution is operable
  5. Go-live decisionTaken in Deploy on the evidence above
Which level's exit criteria feed which SAP Activate decision.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-301
  1. Were all planned test cases executed or formally descoped?Yes → check results · No → not ready; list the gap and its owner
  2. Are there open S1 defects?No → check S2 · Yes → not ready unless the decision owner accepts the risk in writing
  3. Do all S2 defects have an approved workaround and target date?Yes → check critical processes · No → not ready
  4. Did every named critical process pass end to end?Yes → recommend exit · No → not ready for that process
An exit check for SIT, driven by criteria the strategy set.
The Sign-Off Table · thesignofftable.com/academy/sap-tst-301

Metrics that evidence the criteria

MetricWhat it showsSource at Contoso
Execution progressExecuted versus planned, by plan and processCloud ALM Test Execution Analysis
Pass rate by processWhere quality is good or poorTest Execution Analysis by scope
Open defects by severity and ageRisk and fixing speedDefect reporting
Retest closureDefects closed only after a passed retestDefects linked to passed runs
Requirement coverageApproved requirements with passed testsRequirement Traceability
Process readinessProcesses with requirements confirmed and tests passedSolution Process Traceability

Metrics mapped to the criteria they evidence.

Choose a small set. Every metric should evidence a criterion or flag a risk early. Defect age is a good early warning: S2 defects older than five days usually mean the fix capacity is short, long before the pass rate shows it.

Reporting cadence and audiences

AudienceCadenceContent
Test team and build leadsDaily during cyclesBlocked tests, new S1 and S2 defects, retests due
Program leadership (Grace)WeeklyProgress against plan, risks, decisions needed
Steering committeeMonthly and at gatesReadiness by process, criteria status, recommendation
Process owners (Dan, Maria)At UAT start and exitResults for their processes, open defects and workarounds

Reporting plan.

The test status report and test completion report in ISO/IEC/IEEE 29119-3 correspond to the weekly report and the cycle exit report. A completion report should state the criteria, the actual results, the deviations and the recommendation, and it should be the document the gate decision refers to.

What would you do?

At Contoso's SIT 2 exit, the pass rate is 93% against a 95% threshold. The failures are three S3 defects in output forms and one S2 defect in fleet pricing with a manual workaround. The program director wants to "round up". What should Priya recommend?

Key points
  • Write checkable entry and exit criteria per level and link them to the quality gates they feed.
  • Pair percentage thresholds with severity rules and named critical processes.
  • Use a small set of metrics that evidence criteria, from Cloud ALM analytics where possible.
  • Set reporting cadence by audience; agree criteria before each cycle, and record any exception as a decision.

Check your understanding · not graded

Lesson check

  1. 1. Which is a checkable entry criterion?

  2. 2. Why pair a pass-rate threshold with severity rules?

  3. 3. Which metric gives early warning of short fix capacity?

  4. 4. When should entry and exit criteria be agreed?