Lesson 6 of 6

The 24-month roadmap

16 min

Listen to this lesson

0:00 / 4:52

The overview course (sap-tst-401) sketched the TCoE's first 24 months: foundation, stabilize, automate, scale, optimize. Contoso has lived through the first year of that. This lesson builds the next 24-month roadmap from what the TCoE now knows: the maturity assessment, the KPI gaps in its scorecard, the AI shortlist and guardrails, the skills plan and the calendar of change. It is a plan the quality council can fund, track and stop if needed.

Inputs

InputWhat it saysRoadmap consequence
Maturity assessment (lesson 1)Test Environment partially achieved; non-functional testing not achieved; lifecycle integration and training partialFix Test Environment first; plan non-functional and lifecycle work in year 2
Scorecard (sap-tcoe-406)Escapes 14 a quarter (target under 8); DDP 94%; coverage 80%; key-user hours 64 a yearProcure-to-pay coverage and data; escape root causes; close-week protection
AI shortlist (lesson 2)Adopt failure clustering; pilot test case drafts and data identification; reject autonomous scopeTwo pilots with golden sets, then scale what passes
CalendarTwo feature pack stack updates a year; Wave 2 for company code 1910; Solution Manager 7.2 mainstream maintenance ends in 2027; TMMi 1.3 assessments end after August 1, 2027Land capabilities before stacks; formal assessment on TMMi v2.0
Funding (sap-tcoe-401)Investment released in three tranches by milestoneTranche 3 tied to the month-12 checkpoint

The inputs to Contoso's next roadmap and what each changes.

Four phases

Contoso's next 24 months. Pilots start only after guardrails and literacy are in place, and scale only after they pass.
The Sign-Off Table · thesignofftable.com/academy/sap-tcoe-408
PhaseMonthsMain deliverables
Fix the foundation0 to 6Data recipes for all four value streams; masking automated in the runbook; procure-to-pay automation and data (tranche 2); AI use policy and guardrails; AI literacy for all
Pilot and integrate6 to 12Two AI pilots measured on golden sets; TCoE engaged from Explore for every project above the threshold; KPI history complete for Test Measurement
Scale what works12 to 18Passed pilots extended to all value streams; formal TMMi v2.0 level 2 assessment; outcome component in the partner contract starts
Reach for level 318 to 24Non-functional testing standard for performance and roles; role-based training program; AI quality specialists evaluate the first Joule feature on the release calendar

The four phases and their deliverables.

Checkpoints with teeth

A roadmap without checkpoints is a wish list. Contoso's has four, one per phase, each reviewed by the quality council with a decision: continue, adjust or stop. Each checkpoint names KPIs and their thresholds, so the decision is about evidence, not enthusiasm.

CheckpointEvidence requiredDecision
Month 6Test Environment process area satisfied in an informal reassessment; data-caused failures under 10%; guardrails approved; AI literacy completedRelease the pilots; continue
Month 12Weighted escapes under 10 a quarter; procure-to-pay coverage 100% of critical processes; each pilot at or above its golden-set acceptance criteriaRelease tranche 3; scale passed pilots; stop failed ones
Month 18Formal TMMi v2.0 level 2 achieved; enhancement testing at or below 22 hours per change; key-user hours in close weeks at zeroStart level 3 work; reset targets
Month 24Weighted escapes under 8 a quarter; DDP above 95%; level 3 process areas at least largely achieved in an informal assessmentNext roadmap; consider a formal level 3 assessment

Roadmap checkpoints. The KPIs come from the scorecard in sap-tcoe-406 and the levers in sap-tcoe-401.

  1. Did the phase deliver its evidence?Yes → continue to the next phase · No → next question
  2. Is the gap due to a dependency outside the TCoE?Yes → escalate the dependency and adjust dates · No → next question
  3. Is the item still worth its cost on current evidence?Yes → adjust scope or approach and recheck in three months · No → stop it and record why
The checkpoint decision. Stopping an item that does not work is a success of governance, not a failure.
The Sign-Off Table · thesignofftable.com/academy/sap-tcoe-408

Where an AI-capable automation platform fits

AI in the automation layer sits mostly in phase 2 and 3: failure clustering and flaky-test flags from the start, self-healing with review in every regression, AI-generated data variations under the same review rules as test cases. These features are judged like everything else on the roadmap: a pilot, a golden set or a measured baseline, and a KPI that should move, here regression cycle time, automation stability and enhancement testing hours.

What would you do?

At the month-12 checkpoint, the AI test case drafting pilot scores 55% correct or correctable on the golden set against a 70% threshold, but the analysts like it. What should the quality council decide?

Key points
  • Build the roadmap from the assessment, the scorecard, the AI shortlist, the skills plan, the calendar and the funding model.
  • Phase it: fix the foundation, pilot and integrate, scale what works, reach for level 3.
  • Give each checkpoint KPIs and thresholds, and decide continue, adjust or stop on evidence.
  • Judge AI in automation like any roadmap item: a pilot, a baseline and a KPI that should move.

Check your understanding · not graded

Lesson check

  1. 1. Why does Contoso's roadmap fix Test Environment before scaling AI pilots?

  2. 2. What makes a roadmap checkpoint useful to the quality council?

  3. 3. Why is the formal TMMi assessment planned on v2.0 at month 15?

  4. 4. At month 12, the AI drafting pilot scores 55% against a 70% threshold, but analysts like it. What does the checkpoint rule allow?