Lesson 5 of 5

Pruning the suite

9 min

Listen to this lesson

0:00 / 5:47

Suites grow. Every project adds tests, every defect adds a regression test, and nobody removes anything. After a few releases, the suite takes too long to run, maintenance swallows the team, and many tests protect processes nobody uses any more. Pruning is the deliberate, data-driven retirement of tests whose cost exceeds their value. The ISTQB syllabus includes it in continuous improvement: evaluate existing scripts for revision or elimination, decompose complex and slow tests, and target tests that run rarely or never.

Measure value and cost

Value signalsCost signals
Covers a critical or high-volume business processMaintenance hours per release
Has found defects, or guards a control auditors rely onFlip rate and time spent analyzing false failures
Covers changed areas often (high change frequency)Runtime and environment or data demands
Unique coverage: no other test checks thisOverlap with other tests on the same steps

Signals for judging an automated test's worth.

Usage data from production helps judge process value. On the SAP side, transaction and app usage statistics show which processes users actually run; a test for a transaction that nobody has used for a year protects little. Combine that with your own run history: defects found, failures that were false alarms, and hours spent on each test.

Value and cost come from two sources: production usage for the process, and run history for the test itself.
The Sign-Off Table · thesignofftable.com/academy/sap-tau-303
Keep, low attentionCheap tests of minor processes: keep while they stay cheap.
Retire or replaceCostly tests of minor or unused processes: strongest candidates for retirement.
ProtectCheap tests of critical processes: the core of the suite.
RedesignCostly tests of critical processes: invest to make them cheaper, move checks to API level, split them.
Value versus cost: what to do with each test.
The Sign-Off Table · thesignofftable.com/academy/sap-tau-303

Options short of deletion

  • Split a long end-to-end test into smaller tests so one failure does not hide the rest.
  • Move down a level: replace UI checks of business rules with API or ABAP Unit tests, and keep one UI path.
  • Consolidate tests that repeat the same steps into reusable functions or one parameterized test.
  • Reduce frequency: run low-risk tests weekly instead of nightly.
  • Retire: remove from the active suite, archive in version control, and record the coverage gap.
Work down the options before deleting anything: retire only tests whose process is unused or whose coverage is duplicated, and protect critical ones.
The Sign-Off Table · thesignofftable.com/academy/sap-tau-303

A retirement process

  1. Candidate listEach quarter, rank tests by cost and value from run history and usage data.
  2. ReviewPriya and the automation engineers propose actions: keep, redesign, split, reduce, retire.
  3. Process owner agreementDan, Maria or the relevant owner confirms the business risk of each retirement.
  4. Retire and archiveRemove from the active suite; archive with a tag and the reason.
  5. Record the gapNote which risk is now covered manually, at a lower level, or accepted.
A quarterly pruning cycle with business agreement.
The Sign-Off Table · thesignofftable.com/academy/sap-tau-303

At Contoso, the first pruning review cut the nightly suite from 250 to 205 tests. Thirty-one duplicates created by different project teams and 22 tests of legacy transactions retired by the conversion were removed, and four slow end-to-end tests were split into twelve smaller ones (250 − 53 + 8 = 205). The nightly runtime fell by about a third and maintenance time per feature pack stack dropped noticeably, while coverage of the critical processes did not change.

What would you do?

A 45-minute end-to-end test covering procure-to-pay has flipped 12 times in 60 runs and found no defects in a year. It is the only automated check of purchase order approval over $25,000. What should Priya propose?

Key points
  • Suites grow without pruning; cost eventually exceeds value.
  • Judge tests by value (criticality, unique coverage, defects found) and cost (maintenance, flakiness, runtime).
  • Prefer split, move down a level, consolidate or reduce frequency before retiring.
  • Retire with process owner agreement, archive with a reason and record the coverage gap.
  • Protect tests that guard controls; redesign them instead of removing them.

Check your understanding · not graded

Lesson check

  1. 1. Which test is the strongest candidate for retirement?

  2. 2. Who should agree before a test of a business process is retired?

  3. 3. What does "move down a level" mean when redesigning a costly UI test?

  4. 4. Why are some slow tests marked "protected" in the pruning review?