Pre-Sales: Inquiries, Quotations and Contracts
Course quiz
Pre-Sales: Inquiries, Quotations and Contracts
Keep this: job aid
Pre-sales reference card
- Inquiry (IN, VA11) = interest. Quotation (QT, VA21) = binding offer with valid-from / valid-to.
- Always create orders with reference; never retype quoted prices.
- Copy control (VTAA) decides what is copied; the pricing type decides kept vs re-determined prices.
- Completion rule decides when a partly referenced quotation item is complete.
- Contracts (VA41, Manage Sales Contracts): quantity (CQ) or value → release orders consume the balance.
- Scheduling agreement (LZ, VA31) → deliveries straight from schedule lines; new schedules replace old ones.
- Close lost quotations with a reason for rejection; chase expired-but-open ones.
- Conversion rate = converted ÷ created, by value or count, for a stated period.
- Evidence: predecessor and successor side by side, plus document flow and the predecessor's updated status.