Decision criteria

9 min

Choosing a transition path is one of the largest decisions in a program, and it is hard to reverse. It should be made on explicit criteria, with evidence from analyses such as the SAP Readiness Check, rather than on habit or a partner's preference. Different systems in one landscape can even take different paths.

The main criteria

CriterionPoints toward new implementationPoints toward conversionPoints toward selective data transition
Process fitProcesses need redesignProcesses still fitSome areas redesigned, others kept
Custom codeLittle worth keepingValuable and adaptableSome worth keeping
HistoryNot needed in the systemFull history neededHistory for some units or periods
LandscapeSingle system or non-SAP sourceSingle SAP ERP systemSeveral systems to merge, or a carve-out
Target editionAny, and the only path to Public EditionPrivate Edition or on-premisePrivate Edition or on-premise
Timeline pressureLong enough for redesignTight; technical scope firstDepends on scope; often longer planning
Data qualityPoor data can be cleansed in migrationData must be consistent enough to convertSelection allows leaving poor data behind

Decision criteria for the transition paths. Real decisions weigh several criteria together.

Effort and risk compared

New implementationSystem conversionSelective data transition
Business effortHighest: every process designed, tested and trainedLower: decisions on simplification items, validation and regressionMedium to high, depending on how much is redesigned
Technical effortSystem build, extensions, interfaces, data migrationTechnical conversion, custom code adaptation, rehearsalsTarget build plus table-level transformation design and runs
Main risksScope creep, data migration, change fatigueHidden data and code issues, downtime, "IT only" mindsetData consistency of selections, tool and provider dependency, complexity
ValueMaximum simplification and clean coreFastest technical move; history and investments keptTailored balance; consolidation and phasing
Effort and risk profiles of the three paths.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-102

A worked decision: Contoso

Contoso's program weighed the criteria in its Discover and Prepare phases. The finance director needed ten years of history in the system for audit and warranty analysis. Operations were broadly happy with their processes. Custom code was mixed: some valuable fleet pricing logic, some reports that standard apps would replace. Contoso ran one SAP ERP system. The deadline was tight. And the target was Private Edition under RISE with SAP.

  1. Is the target Public Edition?No → all three paths remain open · Yes would have meant new implementation
  2. Is full history needed in the system?Yes, ten years → conversion or selective data transition
  3. Is there more than one source system, or a carve-out?No, one system → selective data transition loses its main advantage
  4. Do processes still fit, and is time short?Yes and yes → system conversion, with targeted improvements after go-live
How Contoso's criteria led to a system conversion.
The Sign-Off Table · thesignofftable.com/academy/sap-s4t-102

The decision did not mean "no change". Contoso planned the mandatory simplification decisions as part of the conversion, retired custom reports in favor of standard apps, and scheduled process improvements in finance as follow-up projects. That combination, sometimes called a technical conversion with selective innovation, is common.

The decision is also made per system, not only per company. SAP's own examples show landscapes where one country's ERP is converted, another is reimplemented, and finance is consolidated separately. For each system, ask the same questions, and make sure the combined plan still fits the program's budget, its testing capacity and its cutover calendar, because two paths in one program mean two kinds of testing running side by side.

What would you do?

A retailer's SAP ERP system is twenty years old, heavily modified, and its processes no longer match a new business model. It needs only open items and two years of sales history for analytics, which can be kept in a data warehouse. Which path should the architects recommend evaluating first?

Key points
  • Decide on explicit criteria: process fit, custom code, history, landscape, target edition, timeline, data quality.
  • Compare effort and risk: new implementation is heaviest on business change; conversion on technical and data consistency; SDT on selection complexity.
  • Contoso chose a system conversion: full history, fitting processes, one system, tight deadline, Private Edition.
  • Record the decision with its evidence and trade-offs.

Check your understanding · not graded

Lesson check

  1. 1. A company needs full transaction history in the system and its processes still fit. Which path is a strong candidate?

  2. 2. Which criterion rules out conversion entirely?

  3. 3. Why did selective data transition offer little extra for Contoso?

  4. 4. What is a main risk profile of system conversion?