Manufacturing Changes from SAP ECC to SAP S/4HANA

Course quiz

Manufacturing Changes from SAP ECC to SAP S/4HANA

Keep this: job aid

ECC to SAP S/4HANA manufacturing change card

  • Find your items: Readiness Check and SI check on production data, then read each business impact note.
  • MRP Live (MD01N): no MRP lists, no creation indicators, no MRP type VV; restrictions in SAP Note 1914010.
  • Storage location MRP → MRP areas (ND for excluded, VB for separately planned); run MRP_AREA_STORAGE_LOC_MIGRATION.
  • Production versions are mandatory; CS_BOM_PRODVER_MIGRATION / ...02 can create them.
  • Planning file: new table; set up with PPH_SETUP_MRPRECORDS.
  • Compatibility scope (MRP lists, forecast-based planning): limited rights; check SAP Note 2269324.
  • Embedded PP/DS: finite planning for critical materials; Enhanced LoB function, confirm licensing.
  • Custom code: MRP BAdIs to AMDP; MRP-list reports go stale; ATC does not find everything.
  • Regression: MRP comparison on frozen identical data; costing on a reference order; DTV for before/after.
  • Sign-off: differences explained, values reconciled, production versions and MRP areas complete.