Lesson 2 of 6

Independent quality assessment

12 min

When indicators point to trouble, the program needs a shared, credible picture of where it really stands. People inside the program are too close to provide it, and the steering committee no longer fully trusts the reports. An independent quality assessment provides that picture: a short, evidence-based review by people who are not responsible for the work being reviewed.

Independence and scope

Independence means the reviewers do not report to the people whose work they assess and have nothing to gain from a particular conclusion. It can be an internal assurance team from another part of the company, an experienced program leader from another business unit, or an external reviewer. Public sector project assurance offers a useful model: the UK government's gate review process provides independent guidance to the senior responsible owner, based on evidence that should be available before the review starts, including documents and interviews, and gives a realistic view of the program's chances of success.

Set the scope in a short terms of reference: the questions to answer, the areas in scope, the evidence the reviewers can access, the people they can interview, the time box and who receives the report. For a troubled SAP program the core question is usually simple: can this program reach a defensible go-live, and if so, when and on what conditions?

  1. Days 1–2Terms of referenceQuestions, scope, access, interviewees, sponsor agreed
  2. Days 3–7Evidence collectionDocuments, tool data, interviews, walkthroughs
  3. Days 8–10AnalysisFindings by area; root causes; options
  4. Day 11Read-out to program leadsFactual accuracy check; no surprises
  5. Day 12Report to sponsorDelivery confidence rating, findings, recommendations
A two-to-three week independent assessment, typical for a program of Contoso's size.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-401

Evidence, not opinion

The assessment's strength is its evidence. Reviewers look at what exists and what it shows, rather than at what people say about it. Interviews are evidence too, but they are used to explain the data and find causes, not to replace it.

Tool dataTest plans, execution status and defects from SAP Cloud ALM; requirements and their status; transport history
DocumentsTest strategy, entry and exit criteria, gate decisions, RAID log, cutover plan, mock results
WalkthroughsSample of test cases re-traced from requirement to evidence; a process demonstrated end to end
Re-executionA small sample of passed test cases run again by the reviewer with a key user
InterviewsWorkstream leads, key users, partner leads, sponsor: causes, constraints, confidence
Evidence sources for an independent assessment, strongest at the top.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-401

Sampling and re-execution

A small, well-chosen sample tells you a lot. In the what-if, the reviewer picks 20 test cases marked passed in SIT, across order-to-cash, procure-to-pay and finance, and re-traces each from requirement to evidence. Six have no evidence attached, three were passed with a workaround nobody had approved, and two fail when re-executed with Maria because a pricing condition for Great Lakes Fleet Services had changed since. A pass rate reported at 88% now has a credible error bar.

Sample resultCount of 20What it means
Passed with complete evidence9Reliable
Passed, evidence missing6Status unproven; re-test or retrieve evidence
Passed with unapproved workaround3Hidden risk; process owner must decide
Failed on re-execution2Regression or data change; reported status is wrong

Re-tracing a sample of "passed" cases. Fewer than half were fully reliable.

Findings and the confidence rating

The report should be short: an overall delivery confidence rating (for example on a red, amber, green scale with defined meanings), five to ten findings ranked by impact, the root cause behind each, and recommendations with owners. Each finding links to the evidence that supports it. Avoid long lists of minor observations; they bury the few issues that decide the outcome.

RatingMeaningTypical response
GreenLikely to deliver on time and to quality; no major open issuesProceed; address minor recommendations
AmberAchievable, but significant issues need management action nowTargeted recovery actions; re-check at the next gate
RedNot achievable on the current plan without major changeRe-baseline scope, plan or date; consider pausing
A simple delivery confidence scale. Define the meanings before the review, not after.
The Sign-Off Table · thesignofftable.com/academy/sap-pmo-401

What would you do?

The systems integrator's account lead proposes that his own quality team performs the assessment, because they know the solution best. What should the sponsor decide?

Key points
  • An independent assessment gives a credible picture when internal reporting has lost trust.
  • Write terms of reference: questions, scope, access, interviewees, time box, recipient.
  • Prefer tool data, documents, walkthroughs and re-execution; use interviews to explain causes.
  • Report a defined confidence rating and a few evidence-linked findings; protect the messengers.

Check your understanding · not graded

Lesson check

  1. 1. What makes a quality assessment independent?

  2. 2. Which is the strongest form of evidence in an assessment?

  3. 3. What should the terms of reference define?

  4. 4. Why should confidence rating meanings be defined before the review?