Hypercare and Transition to Run
Course quiz
Hypercare and Transition to Run
Keep this: job aid
Hypercare lead's checklist
- Hypercare plan approved at go/no-go: roster, hours, tiers, ticket categories, priorities, fix path.
- Key users booked for floor support in week one at every site.
- SAP Cloud ALM monitoring and alerts tested before go-live; business KPIs compared daily with a normal legacy day.
- Every issue is a ticket; triage by fixed categories; priorities by impact and workaround.
- Fixes follow an expedited but controlled path: test, regression of the affected process, approval, release slot.
- Exit criteria agreed before go-live: ticket trend, no P1, owned backlog, first close, KPIs, handover.
- Extend only for named gaps, with a new review date.
- Staged transition: shadow, reverse shadow, first line alone, signed acceptance.
- Handover pack: tickets, known errors, documentation, runbooks, monitoring, test assets, contacts.
- Regression suite seeded from SIT and UAT, grown from hypercare incidents, run per release.