Lesson 3 of 6

Volume checks: planning peak-load tests with IT

9 min

Listen to this lesson

0:00 / 6:17

A warehouse runs on minutes. If wave release takes 15 minutes instead of 2, or each RF screen takes 3 seconds instead of under one, a shift loses hours, and the 16:00 truck leaves late. Functional tests with five deliveries will never show this. Volume checks do, but only if the business defines what "fast enough" means and IT designs a test that recreates the real peak.

Define the peak in business terms

Start with numbers Marcus recognizes, not technical metrics. Contoso's peak is the last working day of the quarter, when fleet customers order before budget closes:

MeasureNormal dayPeak day (planning basis)
Outbound delivery items6001,200
Deliveries150300
Inbound trucks1225
Concurrent RF users3045
Wave releases46, the largest with about 400 items
Cycle count documents400 (suspended on peak days)

Contoso's warehouse 1710 volumes. Figures are the project's planning assumptions.

Agree thresholds the business can accept

Thresholds turn "it feels slow" into pass or fail. Each one should come from a business consequence: how long can the PM wave take to release before pickers stand idle? How long can an RF screen take before scanners queue? Sam and Priya propose numbers; Marcus accepts them, because they live with the result.

Every threshold starts from a business consequence that Marcus recognizes, so a miss in testing is a business problem, not just a number.
The Sign-Off Table · thesignofftable.com/academy/sap-ewm-301
StepThreshold (Contoso)Business reason
RF screen response (scan to next screen)95% under 1 second, none over 3 secondsPickers scan hundreds of times per shift
Release of the largest wave (about 400 items)Under 3 minutes to all warehouse orders createdPickers wait for work after release
Goods issue for one deliveryUnder 10 secondsTrucks queue at doors
Planned replenishment night jobFinishes before 05:00First wave starts at 06:00
Physical inventory clearing jobFinishes within its batch windowDoes not block morning work

Performance thresholds Marcus signed off before testing.

Design the test with IT

  1. Volume dataLoad realistic stock, bins and open orders into the test system (similar occupancy to production)
  2. Background loadRun the night jobs and interfaces that will run in production at the same time
  3. Generate demandCreate peak volumes of deliveries and inbound deliveries
  4. Release and executeRelease the peak waves; real or scripted RF users confirm tasks in parallel
  5. MeasureResponse times, job runtimes and warehouse order creation logs
  6. CompareAgainst the thresholds; analyze anything that misses
The shape of Contoso's warehouse volume test.
The Sign-Off Table · thesignofftable.com/academy/sap-ewm-301

Some practical points. A volume test needs a system sized like production; Sam confirms with the RISE team which system can carry it. Warehouse order creation and wave release are where EWM does heavy work, so activate the warehouse order creation log (/SCWM/ACTLOG) for analysis, and remember to switch logging off afterwards because logs add load. Use the warehouse management monitor and EWM's measurement services or the Warehouse KPIs app to watch open tasks and backlogs during the run. Automated RF scripts can generate load, but at least some real users on real devices should run in parallel, because they feel what the numbers mean.

One peak-day volume run: background load and demand first, then the largest wave release and parallel RF work, measured against the signed thresholds.
The Sign-Off Table · thesignofftable.com/academy/sap-ewm-301
  1. Week −10Thresholds agreedMarcus signs the peak definition and thresholds
  2. Week −8Test design and dataSam and Priya prepare data, scripts and monitoring
  3. Week −6First volume runBaseline; defects raised for misses
  4. Week −4Retest after fixesSecond run with fixes and tuned settings
  5. Week −2Final confirmationRun during the dress rehearsal window if possible
Where volume checks sit in Contoso's plan before the Q3 go-live.
The Sign-Off Table · thesignofftable.com/academy/sap-ewm-301

What would you do?

The first volume run releases the 400-item wave in 11 minutes against a 3-minute threshold. Everything else passes. What is the best next step?

MeasureThresholdRun 1Run 2 (after fixes)
Largest wave release (about 400 items)Under 3 min11 min2 min 20 s
RF screen response, 95th percentileUnder 1 s0.8 s0.7 s
Goods issue per deliveryUnder 10 s6 s5 s
Planned replenishment night jobDone before 05:0004:1003:55

Illustrative course data: Contoso's volume runs against the signed thresholds. The wave fix was an index on a custom table read in the warehouse order creation enhancement.

Key points
  • Define the peak in business numbers that the process owner recognizes.
  • Agree thresholds based on business consequences before testing.
  • Recreate production conditions: data volume, background jobs, interfaces and parallel RF users.
  • Analyze misses with logs and custom code review, fix, and rerun.

Check your understanding · not graded

Lesson check

  1. 1. Who should accept the warehouse performance thresholds?

  2. 2. Why run night jobs and interfaces during a volume test?

  3. 3. Which log helps analyze slow warehouse order creation?

  4. 4. Why switch logging off after the volume test?