Pilot, parallel run and cutover

16 min

Listen to this lesson

0:00 / 13:14

Certification proves the partner's and Contoso's systems agree on test data. Production adds real volume, real people and real exceptions. A pilot or parallel run is the controlled way to meet them before the whole relationship depends on EDI.

Three ways to start

ApproachHow it worksRisk it controlsRisk it adds
PilotA subset goes live first, such as two depots or one product family; the rest stays on the old channelLimits the blast radius of an unknown defectTwo channels to run and reconcile for a few weeks
Parallel runThe partner sends EDI and the old channel for the same orders; only one is processed, the other comparedProves EDI produces the same orders as the trusted channelDuplicates if both are processed; double work for both sides
Big bangAll volume switches at once on the cutover dateNo dual runningEvery defect hits all orders at once
Pilot, parallel run and big bang compared for a new EDI partner.
The Sign-Off Table · thesignofftable.com/academy/sap-edi-304

For Northern Plains, Contoso chooses a pilot: depots D07 and D02 order by EDI for two weeks, the other nine keep e-mailing orders to Maria's team. A parallel run would have meant Northern Plains sending every order twice, which their coordinator declined, and Contoso would have had to block one channel's orders to avoid duplicates.

Volume limits and guardrails

A pilot needs explicit limits, written in the cutover plan: which depots or products, how many orders per day, and what happens if a limit is exceeded. Add guardrails in the system too. Contoso's are simple: EDI orders from Northern Plains during the pilot use the normal order type but receive a delivery block that Maria's team removes after a quick review, so a mapping defect can't ship the wrong alternators before someone looks. The block is removed from the process at full go-live.

What to monitor every day

  • Counts by document: 850s received, orders created, 855s sent; deliveries with goods issue and 856s sent; billing documents and 810s sent.
  • Acknowledgments: every outbound document has an accepted 997 within the agreed 4 hours; in TPM, nothing sits in Waiting for Acknowledgment or Acknowledgment Overdue.
  • Errors: IDocs in status 51, failed or unassigned interchanges in the B2B monitor, negative MDNs.
  • Business results: Maria's review findings, and the partner's feedback on 856 and 810 matching.
Contoso's daily pilot reconciliation: a day counts as clean only when counts, acknowledgments and business review all agree.
The Sign-Off Table · thesignofftable.com/academy/sap-edi-304

Deciding to cut over

Agree the cutover criteria before the pilot starts, so the decision isn't made under pressure. Contoso's criteria for Northern Plains: ten consecutive clean business days; no open severity 1 or 2 defects; every document type exercised in production at least five times, including one partial shipment and one credit memo; daily reconciliation at 100 percent; and the partner's written agreement. Grace's decision group doesn't need to meet for one partner; Maria and Priya decide, and Theo confirms the technical readiness.

Extend the pilotLittle volume, little evidence: keep the pilot running until the criteria are met.
Ready to cut overLittle volume so far, but criteria met and evidence clean: switch the rest.
Stop and fixHigh volume on EDI with weak evidence: reduce to the pilot scope.
Business as usualFull volume with strong evidence: hand over to support.
Where a partner's rollout stands, and the next move from each quadrant.
The Sign-Off Table · thesignofftable.com/academy/sap-edi-304

What would you do?

After eight clean pilot days, Northern Plains asks to switch all 11 depots tomorrow because a large order is coming. No credit memo has been tested in production yet. What should Maria and Priya decide?

Key points
  • Choose pilot, parallel run or big bang deliberately; a pilot limits blast radius, a parallel run risks duplicates.
  • Write pilot limits and system guardrails, such as a delivery block for review, into the cutover plan.
  • Reconcile counts, acknowledgments, errors and business results every day; only then is a day clean.
  • Agree cutover criteria before the pilot and keep them under pressure.

Check your understanding · not graded

Lesson check

  1. 1. What is the main risk of a parallel run in which the partner sends both EDI and e-mail orders?

  2. 2. Which guardrail did Contoso use during the Northern Plains pilot?

  3. 3. When should cutover criteria be agreed?

  4. 4. Which pilot day counts as clean at Contoso?