Lesson 6 of 6

Mock cycles, dress rehearsal, the evidence pack and hypercare

8 min

Listen to this lesson

0:00 / 12:22

This course discusses ACCELQ by name. Matt Angerer, who runs The Sign-Off Table, works at ACCELQ. Disclosure

Every check in this course pays off only if it runs the same way in every rehearsal and on the go-live weekend, and if its result ends up in front of the people who sign. This lesson puts the pieces into a cycle plan for Contoso's Wave 2, defines what tightens from one cycle to the next, lists the evidence pack, and sets the conditions for leaving hypercare. Wave 2 is in progress: W2 Mock 1 starts in late October 2026, and the go-live weekend is planned for Friday, February 5, 2027, 18:00 to Sunday, February 7, 10:00, a 40-hour window.

Contoso's planned Wave 2 cycles: each mock leaves time for root-cause analysis, fixes and retests before the next.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-305

Each cycle is stricter than the last

SAP Business Transformation Center formalizes a useful pattern for its lean selective data transition: a test cycle, in which errors can be bypassed so the team can tune iteratively; a dress-rehearsal cycle, intended to practice the productive cutover with parameters close or equal to it, in which errors block all further steps; and a go-live cycle. Contoso's Wave 2 uses the Migration Cockpit, not BTC, but adopts the same discipline: what may be waived in W2 Mock 1 blocks in the dress rehearsal.

CyclePurposeRules and dataExit criteria
W2 Mock 1Every object attempted; problems knownDraft mappings; subset allowedAll nine reconciliation layers run; baseline and rerun regression done; defects logged
W2 Mock 2Full volume; errors explainedFull extract; mappings signedAll differences explained; volume measured; interfaces passed end to end
W2 Mock 3Timing inside the 40-hour windowFrozen rules and runbookCritical objects near zero errors; window met with contingency; untouched check clean
W2 dress rehearsalPractice the weekendProduction rules, production-like timingNo blocking differences; go/no-go criteria all evidenced; fallback rehearsed
Go-liveProduction loadAs rehearsedSigned reconciliation, regression, interface and access results; decision group's go

Wave 2 entry and exit criteria tighten from cycle to cycle.

Two rules make the cycles comparable. The same checks run every time: SAP describes reusing LTVF rules across test cycles, dress rehearsals and the production cutover, and the same idea applies to Contoso's saved report variants and regression rows. And the trend is reported, not just the latest result: open differences should fall sharply from W2 Mock 1 to W2 Mock 3, with source-data and mapping causes disappearing first. A flat curve two weeks before the dress rehearsal is a schedule risk, whatever the latest pass rate says.

Running the checks on every cycle

Manual checks drift between cycles; automated ones do not. With ACCELQ as the automation layer, the regression suite and API checks can be packaged as a CI Job and started from a pipeline or through ACCELQ's REST trigger when Luis's runbook marks the load complete, passing run properties such as the cycle name. ACCELQ's external API returns run results with pass, fail and not-run counts, which the evidence pack can store with the cycle. The reconciliation itself stays in SAP's reports and tools and with Dan.

After every W2 load the same three streams run and feed one differences log, judged against that cycle's criteria.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-305

The evidence pack

SectionContentsSigned by
ReconciliationNine-layer results for 1910 per cycle, untouched snapshots for 1710 and 1810, intercompany checksDan
Accepted differencesEach difference with cause, amount, decision and approverDan, or the owner of the object
RegressionBaseline and rerun reports per cycle, output comparison by company codeMaria (1710), Lucía (1910), Dan (finance outputs)
InterfacesConnectivity, functional, negative, switch-off and volume results; partner confirmationsTheo with Lucía
AccessRole tests, Access Control risk analysis, emergency access logNadia
VolumeJob runtimes against windows at full volumeSam
CutoverRunbook with planned and actual timestamps, fallback rehearsal resultLuis
DecisionGo/no-go criteria, minutes and the decision group's decisionGrace's decision group

The Wave 2 evidence pack: one section per stream, one signer per section.

Hypercare and its exit

Problems after a consolidation often surface weeks later, at the first period-end, the first payment cycle with a new bank format or the first quarter-end consolidation. EY frames carve-out reporting as Day 1, Month 1 and Quarter 1; use the same frame for hypercare. Contoso keeps Wave 2 hypercare open through the February month-end close and the first quarter-end close for 1910 in April 2027, which also falls before the TSA ends on April 30, so the legacy ERP is still there if a balance needs tracing. Exit criteria: two clean month-end closes for 1910, no open severity 1 or 2 defects, first quarter consolidated in Group Reporting without manual 1910 adjustments, CFDI rejection rate at its agreed level, and a tested path to legacy history after the TSA.

  1. Day 1 (Feb 8, 2027)First business dayOrders, deliveries and CFDI invoices for 1910; untouched check repeated for 1710 and 1810 on production
  2. Week 1First payment runMXN payment files accepted by the bank; bank statements matched
  3. Month 1February closeFirst 1910 month-end close in SAP S/4HANA; intercompany with 1710 reconciled
  4. Quarter 1Quarter-end close1910 consolidated in Group Reporting without manual adjustments; hypercare exit decision
  5. April 30, 2027TSA endsLegacy history reachable through the tested read-only path
Hypercare milestones for Wave 2 follow the Day 1, Month 1, Quarter 1 frame and end before the TSA does.
The Sign-Off Table · thesignofftable.com/academy/sap-dmg-305

What would you do?

At the W2 dress rehearsal, all reconciliations tie except open AP in 1910, which differs by MXN 3,214.60 on two suppliers. The team says the same difference appeared in W2 Mock 3 and "was accepted". The accepted-differences log has no entry. What should Priya do before the go/no-go?

Key points
  • Plan W2 Mock 1 to 3 and a dress rehearsal with time to fix and retest between them.
  • Tighten rules each cycle: what is waived in Mock 1 blocks in the dress rehearsal.
  • Run the same versioned checks every cycle, triggered by the runbook, and report the trend.
  • The evidence pack has one section and one signer per stream; hypercare runs through the first quarter-end close.

Check your understanding · not graded

Lesson check

  1. 1. In SAP BTC's cycle types, what happens to errors in a dress-rehearsal cycle?

  2. 2. What should the trend in open reconciliation differences look like from W2 Mock 1 to W2 Mock 3?

  3. 3. Why does Contoso keep hypercare open through the first quarter-end close?

  4. 4. A difference was accepted verbally in W2 Mock 3 but is not in the log. How should the team treat it at the dress rehearsal?