Lesson 5 of 5

Specifying test environments

10 min

Listen to this lesson

0:00 / 6:55

A test environment is more than a system. It is a system and client, plus the right transports, data, users, interfaces, background jobs and tools, available on the dates the plan needs them. When any one of these is missing, testers lose days, or worse, they pass tests that should have failed. The architect's job is to specify the environment per test type, early enough that Basis and SAP can deliver it.

One environment per test purpose

Test typeEnvironment at ContosoDataInterfaces
Unit testCMD 300 and cmc-ext-devSmall sample data created by the developerStubs or development endpoints
Integration and system testCMQ 100 and cmc-ext-testRefreshed production copy, scrambled where personalPartner test endpoints, for example Great Lakes Fleet Services' test system
User acceptance testCMQ 100As integration, plus business-prepared scenariosAs integration
RegressionCMQ 100 during the program; CMR 100 after go-liveStable regression data set, reset per cyclePartner test endpoints or simulated responses
PerformanceCMR 100 and cmc-ext-preprodProduction volumesProduction-like endpoints with agreed load limits
Cutover rehearsalCMQ 100, refreshed from CMPFresh production copyAs production, with outbound messages blocked
TrainingCMQ 200Stable training data, rebuilt per class cycleNone, or simulated

Contoso's test environment map. Each test type has one named home.

Data: refresh, protect, reset

Production-like data is what makes a quality or pre-production system worth having, and it is also where privacy risk lives. Contoso refreshes on a planned schedule rather than at random: CMR quarterly, before each release regression window, and CMQ before major project test cycles. In the private edition, homogeneous system copies of ABAP systems are a service SAP includes up to a stated number per system per contract year after the initial build; each is requested with a lead time. After every copy, a post-copy checklist runs: personal data scrambled, interfaces repointed, outbound email and payment files blocked, test users restored, jobs reviewed.

  1. RequestSam requests the CMP → CMQ copy with dates agreed with Priya
  2. CopySAP performs the system copy within the contract allowance
  3. ProtectPersonal data scrambled; outbound channels blocked
  4. RepointRFC destinations, BTP destinations and partner endpoints set to test targets
  5. RestoreTest users, roles and regression data sets restored
  6. VerifySmoke tests and an environment checklist signed before testing resumes
Contoso's refresh procedure for CMQ. The verify step is an entry criterion.
The Sign-Off Table · thesignofftable.com/academy/sap-arc-202

Integrations: the usual weak spot

Interfaces fail tests for environmental reasons more often than for functional ones: a partner's test system is down, a certificate expired, a destination still points to the previous target. RISE contracts also let SAP configure communication restrictions between production and non-production tiers, which is good protection, but it means a test system cannot reach a production endpoint even by accident, so test endpoints must exist. For each interface, the environment specification names the test counterpart, who owns it, when it is available and what to do when it is not, for example a simulated response.

RISE communication restrictions stop a test system reaching production endpoints, so every interface needs a test counterpart or a simulated response.
The Sign-Off Table · thesignofftable.com/academy/sap-arc-202

Users and roles in test environments

Test users should hold the same business roles that real users will hold, not broad technical authorizations. Contoso creates test users per business role, for example an order-to-cash clerk for sales area 1710 / 10 / 00 and a separate accounts payable clerk like Ana's role, so that a test passes only if the role allows it. Broad authorizations hide missing ones: a tester with full access will never find that the clerk role cannot release a billing document. After each refresh, these users and their role assignments are restored from a documented list, because a production copy brings production users with it.

The environment specification

  • System, client and BTP subaccount for each test type, with the transport level expected.
  • Data source, refresh date, protection steps and reset method.
  • Test users and roles, mirroring the business roles being tested.
  • Interface counterparts, owners, availability and fallback.
  • Background jobs that must run, and those that must be stopped.
  • Tools: test management in SAP Cloud ALM, automation and monitoring access.
  • Entry checklist and who signs it before a cycle starts.
The environment checklist is an entry criterion: a cycle starts only when it is signed, and results from a failed environment are re-run.
The Sign-Off Table · thesignofftable.com/academy/sap-arc-202
Cheap and misleadingDevelopment-like data and stubs. Fine for unit tests only
Over-engineered earlyExpensive copies used for tests that do not need them
Fit for integrationRefreshed copies with test endpoints; the workhorse for CMQ
Fit for final proofProduction volumes and endpoints; reserved for CMR rehearsals and performance
Match the environment to the question the test must answer.
The Sign-Off Table · thesignofftable.com/academy/sap-arc-202

What would you do?

Priya's test cycle starts Monday. On Friday, Sam reports the CMQ refresh finished, but the post-copy checklist is incomplete: interfaces still point to the production endpoints copied from CMP. What should Priya do?

Key points
  • Specify each test type's environment: system, client, subaccount, data, users, interfaces, jobs and tools.
  • Refresh on a planned schedule; protect personal data and repoint interfaces after every copy.
  • In the private edition, system copies are requested services within a contract allowance and lead time.
  • An environment checklist is an entry criterion; results from a failed environment are re-run.

Check your understanding · not graded

Lesson check

  1. 1. What should happen after every production-to-quality copy?

  2. 2. Which environment does Contoso use for performance tests?

  3. 3. Why must test endpoints exist for every interface in a RISE landscape?

  4. 4. What should happen to results from an environment that failed its checklist?