The Sign-Off Table
The RISE Testing Playbook

Week 8 of 12

SIT and UAT that hold up

Integration testing proves the processes work across modules and systems. User acceptance proves the business will accept them. Both fail in the same ways: transaction-by-transaction scripts, test users with SAP_ALL, expected results like "screen appears", and no agreed exit criteria.

Everything from the last seven weeks feeds this: the strategy’s exit criteria, the process library’s critical list, the test data rules and the interface inventory.

This week: make SIT and UAT end-to-end, role-based and signable

  1. Write SIT scenarios as end-to-end chains, e.g. EDI order → credit check → delivery → goods issue → billing → invoice to EDI → bank statement clears the payment.
  2. Every expected result must be checkable: a document number, a posted amount, a status. Never "screen appears".
  3. Run UAT with production business roles, one test user per tester, and never SAP_ALL.
  4. Agree the UAT sign-off route and escalation now: process owner, functional lead, test manager, program director.

Number of the week

1

test user per tester is the rule that removes lock conflicts and makes UAT results trustworthy.

Source: The Sign-Off Table UAT plan

Use this week

Next week: the data you migrate is under test too. We set up mock conversions and reconciliation.