Testing an SAP S/4HANA Conversion End to End
Course quiz
Testing an SAP S/4HANA Conversion End to End
Keep this: job aid
Conversion test strategy card
- Write a test question for every iteration: sandbox, CMD, CMQ, mocks, dress rehearsal, production.
- Run the same checks each iteration; use production copies as early as possible.
- Technical gate: SUM clean, follow-on activities verified, SDMI complete, smoke checks passed.
- Finance: close period, pre-checks, before/after extracts with the same reports, zero tolerance unless explained.
- Document every accepted migration error with cause, follow-up and Dan's acceptance.
- Map custom code findings to processes; retire unused code; test by depth of change and criticality.
- Time every runbook step in every mock; measure business downtime, not just technical.
- Keep buffer for validation and a rollback decision point.
- Go/no-go criteria: specific, measurable, owned, agreed before and rehearsed in the dress rehearsal.
- Accept the conversion after hypercare checks; clean up obsolete data only after validation.