Course quiz

User Acceptance Testing for SAP: Planning, Running and Signing Off

Keep this: job aid

UAT planning to sign-off checklist

  • Scope agreed per process owner: processes, variants, roles, testers, exclusions with reasons.
  • Every tester has a user with production-like roles and has passed the logon test.
  • Scripts walked through; each step has data and an observable expected result.
  • Test cases Prepared, grouped into test plans with testers and dates; plan set to In Testing.
  • Evidence per step: document numbers, outputs, screenshots that let a reviewer re-find the transaction.
  • Daily triage: owner, severity, next action and workaround for every new defect.
  • Daily report by process area: executed, passed, failed, blocked, open defects by severity, fixed awaiting retest.
  • Escalate against agreed thresholds, with options and the decision needed.
  • Sign-off pack: scope, coverage, results, open defects, accepted risks, recommendation, signatures.
  • Record each decision as accept, accept with conditions or not accept, with owners and dates.