MRP Live and Material Requirements Planning

Course quiz

MRP Live and Material Requirements Planning

Keep this: job aid

MRP Live test card

  • MRP steps: net requirements → lot size (then min/max, rounding) → scheduling → BOM explosion.
  • Supply counted: stock and firm receipts only; non-firm proposals are recreated.
  • Run: MD01N or Schedule MRP Runs; scope, regenerative vs net change, planning mode, scheduling.
  • No MRP lists: use the stock/requirements list, coverage apps and the run log.
  • Restrictions: SAP Note 1914010 for your release; unsupported materials fall back to classic MRP.
  • Custom ABAP MRP enhancements are not executed by MRP Live; decide retire, redesign or force classic.
  • Coverage: MRP Cockpit → Monitor → Manage Material Coverage → stock/requirements list.
  • MRP areas: plant, storage location, subcontractor; storage location planning replaced.
  • Test: expected type, quantity, dates (factory calendar), segment, messages and engine.
  • Rerun the MRP case set after every support package.