Demand Management and Planning Strategies
Course quiz
Demand Management and Planning Strategies
Keep this: job aid
Demand and strategy cheat sheet
- PIRs: MD61/62/63 or Fiori; right plant, active version, sensible period split.
- Strategy group in MRP 3 selects the strategy; it overrides the MRP group for consumption.
- 10: orders from stock, PIRs reduced at goods issue. 40: orders consume PIRs, overflow planned.
- 20: no PIRs, individual segment, lot-for-lot, sales order stock. 50: VP orders prepare components.
- Consumption modes: 1 backward, 2 back/forward, 3 forward, 4 forward/back; periods in workdays.
- No consumption values = backward 999 days. Consumption runs at order creation or change.
- MD04: live; check segments, available quantity, exception messages (10, 15, 20 for firm receipts).
- Reorganize unconsumed past PIRs (MD74) on a schedule.
- Test: known start, one change, before-and-after lists, expected values written first.
- Cutover: load PIRs before open sales orders.